The Earned Value Management Macros
This macro is used to display planned and projected completion times for the project. Specifically, the status date is shown,
along with the planned finish time, the revised finish time, and the projected finish time.
%EVG_SCHEDULE_PLOT
< ( parameters ) > ;
Note: %EVG_SCHEDULE_PLOT requires output from %EVA_METRICS.
-
ACRONYMS=
long
-
specifies whether the long form of the earned value acronyms is to be used—e.g., BCWP versus EV. The short form is used unless
the macro variable _ACRONYMS_
is set to “long” or ACRONYMS=long is specified. The parameter overrides the macro variable setting; i.e., specifying any non-null value other
than “long” for the ACRONYMS= parameter produces short forms.
-
METRICS=
SAS-data-set
-
identifies the periodic metrics data set produced by the %EVA_METRICS macro, the name of which is determined by the METRICS=
parameter of %EVA_METRICS. The default data set name is METRICS
.
-
PLOT=
SAS-data-set
-
specifies the name of the output data set. This is an internal data set that is used as input to the plotting procedure. The
default data set name is PLOT
.
Table 11.6 summarizes the parameters used for managing input and output data sets in the %EVG_SCHEDULE_PLOT macro.
Table 11.6: %EVG_SCHEDULE_PLOT I/O Parameter Summary
Type
|
Data Set
|
INPUT
|
METRICS
|
OUTPUT
|
PLOT
|