The Earned Value Management Macros
Table 11.11 shows the formulas for the Cost Variance, Schedule Variance, and Variance at Completion, along with the associated percentages.
Table 11.11: Variance Formulas
Acronym
|
Formula
|
CV
|
EV - AC
|
CV%
|
![$\frac{\mr {CV}}{\mr {EV}}$](images/orpmug_evm0009.png)
|
SV
|
EV - PV
|
SV%
|
![$\frac{\mr {SV}}{\mr {PV}}$](images/orpmug_evm0010.png)
|
VAC
|
BAC - EAC
|
VAC%
|
![$\frac{\mr {VAC}}{\mr {BAC}}$](images/orpmug_evm0011.png)
|