Macro Variable _ORCLPEAS_
         
       
         
            
               
                  
Macro Variable _ORCLPEAS_
               
             
          
          
         When you specify the EVALACTSEL= option to evaluate activity selection strategies for a scheduling problem, the CLP procedure defines a macro variable named
            _ORCLPEAS_. This variable contains a character string that describes the solution attempt made with each selection strategy.
            The macro variable contains four terms for each selection strategy that is evaluated; these terms are interpreted as follows:
            
         
         
            
- 
                                ACTSELTYPE
                                
                              
- 
                  indicates the activity selection strategy being evaluated.  
 
          
         
            
- 
                                EVAL_TIME
                                
                              
- 
                  indicates the amount of time taken to evaluate the activity selection strategy. By default, the time reported is CPU time;
                     see the TIMETYPE= option for more information. 
                   
 
          
         
            
- 
                                SOLUTION
                                
                              
- 
                  indicates the index of the solution in the output data set, provided that a solution has been found. Otherwise, SOLUTION=NOT_FOUND.
                     
                   
 
          
         
            
- 
                                REASON
                                
                              
- 
                  indicates the reason a solution was not found. The reason can be either TIME_LIMIT_REACHED or RESTART_LIMIT_REACHED. This
                     term is included only when SOLUTION=NOT_FOUND. 
                   
 
          
         
            
- 
                                MAX_ACTSEL
                                
                              
- 
                  indicates the maximum number of activities selected within the evaluation time.  
 
          
       
         