The CPM Procedure

Input Data Sets and Related Variables

The CPM procedure uses activity, resource, and holiday data from several different data sets with key variable names being used to identify the appropriate information. Table 2.25 lists all of the variables associated with each input data set and their interpretation by the CPM procedure. The variables are grouped according to the statement that they are identified in. Some variables use default names and are not required to be identified in any statement.

Table 2.25: PROC CPM Input Data Sets and Associated Variables

Data Set Statement Variable Name Interpretation
CALEDATACALIDCALIDCalendar corresponding
   to work pattern
    
 DefaultD_LENGTHLength of standard
 names work day
  _SUN_Work pattern on day of
  ...week, valid values:
  _SAT_WORKDAY, HOLIDAY, or one
   of the numeric variables
   in the Workday data set
DATAACTIVITYACTIVITYActivity in AON format
    
 ACTUALA_STARTActual start time of activity
  A_FINISHActual finish time of activity
  REMDURRemaining duration
  PCTCOMPPercentage of work
   completed
    
 ALIGNDATEALIGNDATETime constraint on
   activity
    
 ALIGNTYPEALIGNTYPEType of time constraint,
   valid values: SGE, SEQ,
   SLE, FGE, FEQ, FLE, MS,
   MF
 BASELINEB_STARTBaseline start time
   of activity
  B_FINISHBaseline finish time
   of activity
    
 CALIDCALIDCalendar followed by
   activity
    
 DURATIONDURATIONDuration of activity
  FINISHFinish time of activity
  STARTStart time of activity
    
 HEADNODEHEADNODEHead of arrow (arc) in
   AOA format
    
 IDIDAdditional project
   information
    
 PROJECTPROJECTProject to which activity
   belongs
    
 RESOURCEACTDELAYActivity delay
  ACTPRTYActivity priority
  MAXNSEGMTMaximum number of
   segments
  MINSEGMTDURMinimum duration of a
   segment
  RESOURCEAmount of resource
   required
  WORKAmount of work required
 SUCCESSORSUCCESSORSuccessor in AON format
  LAGNonstandard precedence
   relationship
    
 TAILNODETAILNODETail of arrow (arc) in
   AOA format
HOLIDATACALIDCALIDCalendar to which
   holiday applies
    
 HOLIDAYHOLIDAYStart of holiday
  HOLIDURDuration of holiday
  HOLIFINEnd of holiday
RESOURCEINRESOURCEOBSTYPEType of observation;
   valid values: RESLEVEL,
   RESTYPE, SUPLEVEL,
   RESPRTY, ALTRATE,
   ALTPRTY, RESUSAGE,
   AUXRES, MULTALT,
   MINARATE, CALENDAR
  PERIODTime from which resource
   is available
  RESIDResource for which
   alternates are given
  RESOURCEResource type, priority,
   availability, alternate
   rate, alternate priority
WORKDATA Any numericOn-off pattern of work
  variable(shift definition)