ACTUAL Statement
ACTUAL / actual options ;
The ACTUAL statement identifies
variables in the Activity data set
that contain progress information about the activities in the project.
For a project that is already in progress, you can describe the
actual status of any activity by specifying the activity's
actual start, actual finish, remaining duration, or percent of work
completed. At least one of the four variables
(A_START, A_FINISH, REMDUR,
PCTCOMP) needs to be specified in the
ACTUAL statement. These variables are referred to as progress
variables.
The TIMENOW= option in
this statement represents the value of the current time (referred to
as TIMENOW), and it is used in conjunction with the values of the
progress variables to check for consistency
and to determine default values if necessary.
You can also specify options in the ACTUAL statement that
control the updating of the project schedule. Using the ACTUAL
statement causes four new variables
(A_START, A_FINISH,
A_DUR, and STATUS) to be added to the Schedule data set;
these variables are defined in the section "OUT= Schedule Data Set".
See the section "Progress Updating" for more information.
The following options can be specified in the ACTUAL statement
after a slash (/).
-
A_FINISH=variable
- AF=variable
-
identifies a variable in the
Activity data set that specifies the actual
finish times of activities that are already completed. The actual finish
time of an activity must be less than TIMENOW.
-
A_START=variable
- AS=variable
-
identifies a variable in the Activity data set
that specifies the actual
start times of activities that are in progress or that are already
completed. The actual start time of an activity must be less
than TIMENOW.
-
AUTOUPDT
-
requests that PROC CPM should assume automatic completion (or start)
of activities that are predecessors to activities already
completed (or in progress). For example,
if activity B is a
successor of activity A, and B has an actual start time (or
actual finish time or both)
specified, while A has missing values for both
actual start and actual finish times, then the AUTOUPDT option
causes PROC CPM to
assume that A must have
already finished. PROC CPM then assigns activity A
an actual start time and an actual finish time
consistent with the precedence constraints. The AUTOUPDT option
is the default.
-
ESTIMATEPCTC
- ESTPCTC
- ESTPCTCOMP
- ESTPROG
-
indicates that a variable named PCT_COMP is to be added to the
Schedule output data set (and the Resource Schedule output data set)
that contains the percent completion time for each activity (for each
resource used by each activity) in the project. This
value is 0 for activities that have not yet started and 100 for
completed activities; for activities in progress, this value is
computed using the actual start time, the value of TIMENOW,
and the revised duration of the activity.
-
FIXASTART
-
specifies that the actual start time of an activity should not be
overwritten if it is specified to be on a non-work day. By default,
none of the start or finish times of an activity can occur during a
non-work period corresponding to the activity's calendar. If the
actual start time is specified on a non-work day, it is moved to the
nearest work day. The FIXASTART option specifies that the actual start
and finish times be left unchanged even if they coincide with a
non-working time. Thus, if the actual start time is
specified to be sometime on Sunday, it is left unchanged even if
Sunday is a non-working day in the activity's calendar.
-
NOAUTOUPDT
-
requests that PROC CPM should not
assume automatic completion of activities. (The NOAUTOUPDT option
is the reverse of the AUTOUPDT option.)
In other words, only those
activities that have nonmissing actual start or nonmissing
actual finish times
or both
(either specified as values for the
A_START and A_FINISH variables
or computed on the basis of the REMDUR or
PCTCOMP variables and TIMENOW)
are assumed to have started; all other activities have an implicit
start time that is greater than
or equal to TIMENOW. This option requires you to
enter the progress information for all the activities that have
started or are complete; an activity is assumed to be
pending until
one of the progress variables indicates that it has started.
-
PCTCOMP=variable
- PCTCOMPLETE=variable
- PCOMP=variable
-
identifies a variable in the Activity data set
that specifies the
percentage of the work that has been completed for the current activity.
The values for this variable must be between 0 and 100. A value
of 0 for
this variable means that the current activity has
not yet started. A value of 100 means that the activity is already
complete. Once again, the value of the TIMENOW= option is used
as a reference
point to resolve the values specified for the
PCTCOMP variable. See
the section "Progress Updating" for more information.
-
REMDUR=variable
- RDURATION=variable
- RDUR=variable
-
identifies a variable in the Activity data set
that specifies the
remaining duration of activities that are in progress. The values of
this variable must be nonnegative: a value of 0
for this variable
means that the activity in that observation is completed, while
a value greater than 0 means that the activity
is not yet complete (the remaining duration is used to revise the
estimate of the original duration). The
value of the TIMENOW parameter is used to determine an actual start
time or an actual finish time or both
for activities based on the value of the
remaining duration. See the section "Progress Updating"
for further information.
-
SHOWFLOAT
-
This option in the ACTUAL statement indicates
that PROC CPM should allow
activities that are completed or in progress to have nonzero float. By
default, all activities that are completed or in progress have the late
start schedule set to be equal to the early start schedule and thus have
both total float and free float equal to 0. If the SHOWFLOAT option
is specified, the late start schedule is computed for in-progress and
completed
activities using the precedence and time constraints during the backward
pass.
-
TIMENOW=timenow
- CURRDATE=timenow
-
specifies the SAS date, time, or datetime value that is used as a
reference
point to resolve the values of the remaining duration and percent
completion times when the ACTUAL statement is used.
It can be thought of as the instant at the beginning of the
specified date, when a snapshot of the project is taken;
the actual start times or finish times or both are specified for all
activities that have started or have been completed by the end of
the previous day.
If an ACTUAL
statement is used without specification of the TIMENOW= option,
the default value is set to be the time period following the
maximum of all the actual start and
finish times that have been specified; if there are no actual start or
finish times, then TIMENOW is set to be equal to the current date.
See the section "Progress Updating" for further information
regarding the TIMENOW= option and the ACTUAL statement.
-
TIMENOWSPLT
-
indicates that activities that are in progress at TIMENOW can be split
at TIMENOW if they cause resource infeasibilities. During resource
allocation, any activities with values of
E_START less than TIMENOW
are scheduled even if there are not enough resources (a warning message
is printed to the log if this is the case). This is true even for
activities that are in progress. The TIMENOWSPLT option permits
an activity to be split into two segments at TIMENOW, allowing the
second segment of the activity to be scheduled later when resource
levels permit. See the section "Activity Splitting" for
information regarding activity segments. Activities with
an alignment type of
MS or MF are not allowed to be split; also,
activities without resource requirements will not be split.
Copyright © 2008 by SAS Institute Inc., Cary, NC, USA. All rights reserved.