The RESOURCE statement identifies the variables in the Activity data
set that contain the levels of the various resources required by the
different activities. This statement is necessary if the
procedure is required to summarize resource utilization for various
resources.
This statement is also required when the activities in
the network use limited resources and a schedule is to be determined
subject to resource constraints in addition to
precedence constraints. The levels of the various resources available
are obtained from the RESOURCEIN= data
set (the Resource data set.) This data set need not contain all of the
variables listed in the RESOURCE
statement. If any resource variable specified in the RESOURCE statement
is not also found in the Resource data set, it is assumed to be
available in unlimited quantity and is not used in determining the
constrained schedule.
The following options are available with the RESOURCE statement to
help control scheduling the activities subject to resource
constraints. Some control the scheduling heuristics, some control the
amount of information to be output to the RESOURCEOUT=
data set (the Usage data set), and so on.
-
ACTIVITYPRTY=variable
- ACTPRTY=variable
-
identifies the variable in the Activity data set that contains the
priority of each activity. This option is
required if resource-constrained scheduling
is to be performed and the scheduling rule specified is ACTPRTY.
If the value of the SCHEDRULE= option is specified as the keyword
ACTPRTY, then all activities
waiting for resources are ordered by increasing values of the ACTPRTY=
variable. Missing values of the activity priority variable are
treated as
INFINITY. See the section "Scheduling Method" for a description of the
various scheduling rules used during resource constrained scheduling.
-
ADDCAL
-
requests that a variable, _CAL_, be added to the Resource Schedule
data set that identifies the resource calendar for each resource
used by each activity. For observations that summarize the
activity's schedule, this variable identifies the activity's calendar.
-
ALL
-
is equivalent to specifying the ESPROFILE and
LSPROFILE options when
an unconstrained schedule is obtained and is equivalent
to specifying
all four options,
AVPROFILE (AVP), ESPROFILE (ESP), LSPROFILE (LSP), and
RCPROFILE
(RCP), when a resource-constrained schedule is obtained. If
none of these four options are specified and a
Usage data set is specified, by default
the ALL option is assumed to be in
effect.
-
ALTBEFORESUP
-
indicates that all alternate resources are to be checked first before
using supplementary resources. By default, if supplementary levels of
resources are available, the procedure uses supplementary
levels first and uses alternate resources only if the
supplementary levels are not sufficient.
-
APPEND
- APPENDINTXRATE
- APPENDRATEXINT
- APPENDUSAGE
-
indicates that the Usage data set is to contain two sets of
observations: the first set indicates the rate of usage for each
resource at the beginning of the current time period, and the second
set contains the total usage of each resource for the current time
period. In other words, the Usage data set appends observations
indicating the total usage of each resource to the default set of
observations. If the APPEND option is specified, the procedure adds a
variable named OBS_TYPE to the Usage data set.
This variable contains the value 'RES_RATE' for the observations
that indicate rate of usage and the value 'RES_USED' for the
observations that indicate the total usage.
-
AROUTCAL=calname
-
specifies the name of the calendar to be used for incrementing the
_TIME_ variable in the Usage data set.
-
AVPROFILE
- AVP
- AVL
-
creates one variable in the Usage data set corresponding
to each
variable in the RESOURCE statement. These new variables denote the
amount of resources remaining after resource allocation. This option is
ignored if resource allocation is not performed.
-
AWAITDELAY
-
forces PROC CPM to wait until L_STARTdelay, where
delay is the maximum delay allowed for the activity (which
is the value of the ACTDELAY= variable or the DELAY= option),
before an activity is scheduled using supplementary levels
of resources. By default, even if an activity has a nonzero
value specified for the ACTDELAY= variable (or the DELAY= option),
it may be scheduled using supplementary resources
before L_STARTdelay.
This happens if the procedure does not see any increase in the resource
availability in the future. Thus, if it appears that the activity
will require supplementary resources anyway, the procedure may
schedule it before L_STARTdelay.
The AWAITDELAY option prohibits
this behavior; it will not use supplementary resources to
schedule an activity before L_STARTdelay.
This option can be used to force activities with insufficient
resources to start at L_START by setting DELAY=0.
-
CUMUSAGE
-
specifies that the Usage data set should indicate the
cumulative usage of consumable resources.
Note that by default, for consumable resources, each
observation in the Usage data set contains the rate of
usage for each resource at the start of the given time
interval. See the section "RESOURCEOUT= Usage Data Set"
for a definition of the variables in
the resource usage output data set. In some
applications, it may be useful to obtain the cumulative
usage of these resources. The CUMUSAGE option can be
used to obtain the cumulative usage of consumable
resources up to the time specified in the _TIME_
variable.
[
DELAY=delay]
DELAY= optionRESOURCE statement (CPM)
resource allocation controloptions related to
activity delayspecification
specifies the maximum amount by which an activity can be delayed due to
lack of resources. If E_START of an activity is 1JUN04
and L_START is
5JUN04 and delay is specified as 2,
PROC CPM first tries to schedule the
activity to start on June 1, 2004. If there are not enough resources to
schedule the activity, the CPM procedure
postpones the activity's start time. However, it does not
postpone the activity beyond June 7, 2004
(because delay=2 and L_START=5JUN04).
If the activity cannot be scheduled even on 7JUN04, then PROC CPM
tries to schedule it by using supplementary levels of resources,
if available, or by using alternate resources, if possible.
If resources are still not sufficient, the procedure
stops with an error message. The default value of the DELAY= option
is assumed to be INFINITY.
-
DELAYANALYSIS
- SLIPINF
-
causes the addition of three new variables to the Schedule
data set. The variables are R_DELAY, DELAY_R
and SUPPL_R.
The R_DELAY variable indicates the number of units (in interval units) by
which the activity's schedule has slipped due to resource
unavailability, and the DELAY_R variable contains the name of the
resource,
the delaying resource, that has caused the slippage.
The R_DELAY variable is calculated as follows: it is the difference
between
S_START and the time when an activity first enters
the list of activities that are available to be scheduled.
(See the section "Scheduling Method" for a
definition of this waiting list of activities.)
R_DELAY is not necessarily the same as
S_START - E_START.
If several resources are insufficient, causing a delay in the
activity, DELAY_R is the name of the resource that
first causes an activity to be postponed.
The variable SUPPL_R contains the name of
the first resource that is used above the primary level in
order for an activity to be scheduled at S_START.
-
ESPROFILE
- ESP
- ESS
-
creates one variable in the Usage data set corresponding
to each
variable in the RESOURCE statement. Each new variable denotes the
resource usage based on the early start schedule for the
corresponding resource variable.
-
E_START
-
requests that the E_START and E_FINISH variables, namely the variables
specifying the early start schedule, be included in the Schedule data
set in addition to the S_START and S_FINISH variables.
This option is the default and can be turned off using the NOE_START option.
-
EXCLUNSCHED
-
excludes the resource consumption corresponding to
unscheduled activities from the daily resource usage
reported for each time period in the Usage data set.
The Usage data set contains a variable named
Rresname
for each resource variable resname.
For each observation in this
data set, each such
variable contains the total amount of resource (rate of usage
for a consumable resource) used by all the activities that are active
at the time period corresponding to that observation. By default,
this calculation includes even activities that are still unscheduled
when resource
constrained scheduling is stopped either by the STOPDATE= option or
due to resource infeasibilities. The
EXCLUNSCHED option enables the exclusion of activities
that are still unscheduled. The unscheduled activities are
assumed to start as per the early start schedule
(unless the UPDTUNSCHED option
is specified).
-
FILLUNSCHED
- FILLMISSING
-
fills in S_START and S_FINISH values for activities that are still
unscheduled when resource constrained scheduling is stopped either by
the STOPDATE= option or due to resource infeasibilities. By default, the
Schedule data set contains missing values for S_START
and S_FINISH corresponding
to unscheduled activities. If the FILLUNSCHED option is on, the procedure
uses the original E_START and E_FINISH times for these activities. If
the UPDTUNSCHED option is also specified, the procedure uses
updated values.
-
F_FLOAT
-
requests that the Schedule data set include the F_FLOAT variable computed
using the unconstrained early and late start schedules. If
resource allocation is not performed,
this variable is always included in
the output data set.
-
INCLUNSCHED
-
enables the inclusion of activities that are still unscheduled in the
computation of daily (or cumulative) resource usage in the Usage data
set when resource-constrained scheduling is stopped either by
the STOPDATE= option or due to resource infeasibilities.
This option is the default and can be turned off by the
EXCLUNSCHED option.
-
INDEPENDENTALLOC
- INDEPALLOC
-
enables each resource to be scheduled independently for each activity
during resource-constrained scheduling. Consider the basic resource
scheduling algorithm described in the section "Scheduling Method".
When all the precedence requirements of an activity are satisfied, the
activity is inserted
into the list of activities that are waiting for resources using the
appropriate scheduling rule. An activity in this list is scheduled to
start at a particular time only if all the resources required
by it are available in sufficient quantity. Even if the resources are
required by the activity for different lengths of time, or if the
resources have different calendars, all resources must be available
to start at that particular time (or at the beginning of the next
work period for the resource's calendar).
If you specify the INDEPENDENTALLOC option, however,
each resource is scheduled independently
of the others. This may cause an activity's schedule to be extended
if its resources cannot all start at the same time.
[
INFEASDIAGNOSTIC]
[INFEASDIAG]
INFEASDIAGNOSTIC optionRESOURCE statement (CPM)
INFEASDIAG optionSee INFEASDIAGNOSTIC option
resource allocation controloptions related to
resource allocation controlchecking levels needed
resource infeasibilities
resource allocationanalyzing infeasibilities
infeasibility diagnosticsCPM procedure
diagnose resource infeasibilitiesSee infeasibility diagnostics
requests PROC CPM to continue scheduling even when resources are
insufficient. When PROC CPM schedules the project subject to resource
constraints, the scheduling process is stopped
when the procedure cannot find
sufficient resources for an activity before the activity's latest
possible start time (accounting for the DELAY= or ACTDELAY= options
and using
supplementary or alternate resources if necessary and if allowed). The
INFEASDIAGNOSTIC option can be used to override this default action.
(Sometimes, you may want to know the level of resources needed to
schedule a project to completion even if resources are insufficient.)
This option is equivalent to specifying infinite supplementary levels
for all the resources under consideration; the DELAY= value is assumed
to equal the default value of tex2html_wrap_inline$+$tex2html_wrap_inlineINFINITY, unless otherwise specified.
-
LSPROFILE
- LSP
- LSS
-
creates one variable in the Usage data set corresponding to each
variable in the RESOURCE statement. Each new variable denotes the
resource usage based on the late start schedule for the
corresponding resource variable.
-
L_START
-
requests that the L_START and L_FINISH variables, namely the variables
specifying the late start schedule, be included in the Schedule data
set in addition to the S_START and S_FINISH variables.
This option is the default and can be turned off using the NOL_START option.
-
MAXDATE=maxdate
-
specifies the maximum value of the _TIME_ variable in the
Usage data set. The default value of maxdate is the
maximum finish
time for all of the schedules for which a usage profile was requested.
-
MAXNSEGMT=variable
- MAXNSEG=variable
-
specifies a variable in the Activity data set that indicates the
maximum number of segments that the current activity can be split into.
A missing value for this variable is set to a default value that
depends on the duration of the activity and the value of the
MINSEGMTDUR variable. A value of 1 indicates that the activity cannot
be split.
By default, PROC CPM assumes that any activity, once started, cannot
be stopped until it is completed (except for breaks due to holidays
or weekends). Thus, even during resource-constrained scheduling, an
activity is scheduled only if enough resources can be found for it
throughout its entire duration. Sometimes, you may want
to allow preemption of activities already in progress; thus, a more
critical activity
could cause another activity to be split into
two or more segments.
However, you may not want a particular
activity to be split into too many segments, or
to be split too many times. The MAXNSEGMT= and
MINSEGMTDUR= options
enable you to control the number of splits and the
length of each segment.
[
MAXOBS=max]
MAXOBS= optionRESOURCE statement (CPM)
Usage data setoptions
maximum number of observations (CPM)
specifies an upper limit on the number of observations that the
Usage data set can contain. If the values specified for the
ROUTINTERVAL=
and ROUTINTPER= options are such that the data set will contain more
than max observations,
then PROC CPM does not create the output data
set and stops with an error message.
The MAXOBS= option is useful as a check to
ensure that a very large data set (with several thousands of
observations) is not created due to a wrong specification of the
ROUTINTERVAL= option. For example, if interval is DTYEAR and
routinterval is DTHOUR and the project extends over 2 years,
the number of observations would exceed 15,000.
The default value of the MAXOBS= option is 1000.
-
MILESTONERESOURCE
-
specifies that milestone activities consume resources.
If a nonzero requirement is specified for a milestone, the corresponding
consumable resources are used at the scheduled time of that milestone.
-
MILESTONENORESOURCE
-
specifies that milestone activities do not consume resources. This implies
that all resource requirements are ignored for milestone activities.
This is the default behavior.
-
MINDATE=mindate
-
specifies the minimum value of the _TIME_ variable in the Usage
data set. The default value of mindate is the
minimum start time for all of the schedules for which a usage profile
is requested.
Thus, the Usage data set has observations
containing the resource usage and availability information
from mindate through maxdate .
-
MINSEGMTDUR=variable
- MINSEGD=variable
-
specifies a variable in the Activity data set that indicates the
minimum duration of any segment of the current activity.
A missing value for this variable
is set to a value equal to one fifth of the
activity's duration.
-
MULTIPLEALTERNATES
- MULTALT
-
indicates that multiple alternate resources can be used to substitute
for a single resource. In other words, if one of the alternate resources
is not sufficient to substitute for the primary resource, the procedure will use
other alternates, as needed, to fulfill the resource requirement.
For example, if an activity needs 1.5 programmers
and the allowed alternates are JOHN and MARY, the procedure will use
JOHN (at rate 1) and MARY (at rate 0.5) to allocate a total of 1.5 programmers.
See the section "Specifying Multiple Alternates" for details.
-
NOE_START
-
requests that the E_START and E_FINISH variables, namely the variables
specifying the early start schedule, be dropped from the Schedule data
set. Note that the default is E_START.
Also, if resource allocation is not performed, the NOE_START option
is ignored.
-
NOF_FLOAT
-
requests that the F_FLOAT variable be dropped from the Schedule
data set
when resource-constrained scheduling is requested.
This is the default behavior. To include the F_FLOAT variable
in addition
to the resource-constrained schedule, use the F_FLOAT option.
If resource allocation is not performed, F_FLOAT is always
included in the Schedule data set.
[
NOL_START]
NOLSTART optionNOL_START optionRESOURCE statement (CPM)
Schedule data setoptions to control
requests that the Schedule data set does not include the late start
schedule, namely, the L_START and L_FINISH variables. Note that the
default is L_START. Also, if resource allocation is not
performed, the
NOL_START option is ignored.
-
NORESOURCEVARS
- NORESVARSOUT
- NORESVARS
-
requests that the variables specified in the RESOURCE statement be
dropped from the Schedule data set. By default, all of
the resource variables
specified on the RESOURCE statement are also included in the Schedule
data set.
-
NOT_FLOAT
-
requests that the T_FLOAT variable be dropped from the Schedule
data set
when resource-constrained scheduling is requested.
This is the default behavior. To include the T_FLOAT variable in addition
to the resource-constrained schedule, use the T_FLOAT option.
If resource allocation is not performed, T_FLOAT is always
included in the Schedule data set.
-
NROUTCAL=calnum
-
specifies the number of the calendar to be used
for incrementing the _TIME_ variable in the Usage data
set.
-
OBSTYPE=variable
-
specifies a character variable in the Resource
data set that contains the type identifier for each observation.
Valid values for this variable are RESLEVEL, RESTYPE, RESUSAGE, RESPRTY,
SUPLEVEL, ALTRATE, ALTPRTY, RESRCDUR,
CALENDAR, MULTALT, MINARATE, and AUXRES.
If OBSTYPE= is not specified, then all
observations in the data set are assumed to denote the levels of the
resources, and all resources are assumed to be replenishable and
constraining.
-
PERIOD=variable
- PER=variable
-
identifies the variable in the RESOURCEIN= data set
that specifies the date from which a specified level of the resource
is available for each observation with the OBSTYPE variable equal
to 'RESLEVEL'. It is an error if the PERIOD= variable has a missing value
for any observation specifying the levels of the resources or
if the Resource data set is not sorted in increasing order of
the PERIOD= variable.
-
RCPROFILE
- RCP
- RCS
-
creates one variable in the Usage data set corresponding to each
variable in the RESOURCE statement. Each new variable denotes the
resource usage based on the resource-constrained schedule for the
corresponding resource variable. This option is
ignored if resource allocation is not performed.
[
RESCALINTERSECT]
[RESCALINT]
[RCI]
RESCALINTERSECT optionRESOURCE statement (CPM)
RESCALINT optionSee RESCALINTERSECT option
RCI optionSee RESCALINTERSECT option
multiple calendars and holidaysscheduling during common working times
multiple calendars and holidayscommon working calendar
common working calendar
specifies that an activity can be scheduled only during periods that
are common working times for all resource calendars (corresponding to
the resources used by that activity) and the activity's calendar.
This option is valid only if multiple calendars are in use and if
calendars are associated with individual resources. Use this option
with caution; if an activity uses resources that have mutually disjoint
calendars, that activity can never be scheduled. For example, if one
resource works a night shift while another resource works a day shift,
the two calendars do not have any common working time.
Only primary resources are included in the intersection;
any alternate or auxiliary resources are not included when determining
the common working calendar for the activity.
If you do not specify the RESCALINTERSECT option,
and resources have independent calendars, then the
procedure schedules each resource using its own calendar. Thus, an
activity can have one resource working on a five-day calendar, while
another resource is working on a seven-day calendar.
-
RESID=variable
-
specifies a variable in the RESOURCEIN= data set that indicates the
name of the resource variable for which alternate resource information
or auxiliary resource information is being specified in that
observation.
Observations that indicate alternate resources are
identified by the values 'ALTRATE' and 'ALTPRTY'
for the OBSTYPE variable.
These values
indicate whether the observation specifies a rate
of substitution or a priority for substitution; the value
of the RESID variable in such an observation indicates the
particular resource for which alternate resource information is
specified in that observation.
The specification of the RESID= option
triggers the use of alternate resources. See the section "Specifying Alternate Resources"
for further information.
Observations indicating auxiliary resources are
identified by the value 'AUXRES' for the OBSTYPE variable. Such
observations
specify the name of the primary resource as the value of the
RESID variable and the rate of auxiliary resources needed for every unit
of the primary resource as values of the other resource variables.
See the section "Auxiliary Resources"
for further information.
-
RESOURCEVARS
- RESVARSOUT
-
requests that the variables specified in the RESOURCE statement be
included in the Schedule data set. These include the RESOURCE variables
identifying the resource requirements, the activity priority variable,
the activity delay variable, and any variables specifying activity
splitting information. This option is the default and can be turned off
by the NORESVARSOUT option.
-
ROUTINTERVAL=routinterval
- STEPINT=routinterval
-
specifies the units to be used to determine the time interval between
two successive values of the _TIME_ variable in the Usage
data set. It can be used in conjunction with the ROUTINTPER= option
to control the amount of information to be included in the data set.
Valid values for routinterval are DAY, WORKDAY, WEEK,
MONTH, WEEKDAY,
QTR, YEAR, DTDAY, DTWRKDAY,
DTWEEK, DTMONTH, DTQTR, DTYEAR, DTSECOND,
DTMINUTE, DTHOUR, SECOND, MINUTE, or HOUR.
The value of this parameter must be chosen carefully; a massive amount
of data could be generated by a bad choice.
If this parameter is not specified, a default value is chosen depending
on the format of the schedule variables.
-
ROUTINTPER=routintper
- STEPSIZE=routintper
- STEP=routintper
-
specifies the number of routinterval units between successive
observations in the Usage data set where routinterval is the
value of the ROUTINTERVAL= option. For example,
if routinterval is MONTH and
routintper is 2, the time interval between each pair
of observations in
the Usage data set is two months. The default value of
routintper is 1. If routinterval is blank
(' '), then routintper can be used to
specify the exact numeric interval between two successive values of the
_TIME_ variable in the Usage data set. routintper is
only allowed to have integer values when routinterval is
specified as one of the following: WEEK, MONTH, QTR, YEAR, DTWEEK,
DTMONTH, DTQTR, or DTYEAR.
-
ROUTNOBREAK
- ROUTCONT
-
specifies that the _TIME_ variable is to be
incremented using a calendar with no breaks or holidays. Thus,
the Usage data set contains one observation per unit
routinterval from mindate to maxdate,
without any breaks for holidays
or weekends. By default, the _TIME_
variable is incremented using the default calendar; thus, if the
default calendar follows a five-day work week, the Usage data set
skips weekends.
-
RSCHEDID=(variables)
- RSID=(variables)
-
identifies variables not specified in the TAILNODE, HEADNODE, or
ACTIVITY statements that are to be included in the Resource Schedule
data set. This option is useful for carrying any
relevant information about each activity from the
Activity data set to the Resource Schedule data set.
-
SCHEDRULE=schedrule
- RULE=schedrule
-
specifies the rule to be used to order the list of activities
whose predecessor activities have been completed while scheduling
activities subject to resource constraints. Valid values for
schedrule are LST, LFT, SHORTDUR, ACTPRTY, RESPRTY, and DELAYLST.
(See the section "Scheduling Rules" for more information.)
The default value of SCHEDRULE is LST.
If an invalid specification is given for the SCHEDRULE= option, the
default value is used, and a warning message is displayed in the log.
[
SCHEDRULE2=schedrule2]
[rule2=schedrule2]
SCHEDRULE2= optionRESOURCE statement (CPM)
RULE2= optionSee SCHEDRULE2= option
resource allocation controloptions related to
resource allocation controlscheduling rules
schedulingrule for breaking ties
resource allocationsecondary scheduling rule
specifies the rule to be used to break ties caused by the
SCHEDRULE= option. Valid values for schedrule2 are
LST, LFT, SHORTDUR,
ACTPRTY, RESPRTY, and DELAYLST. ACTPRTY and
RESPRTY cannot be specified at the same time for the
two scheduling rules; in other words, if
schedrule is ACTPRTY,
schedrule2 cannot be RESPRTY and vice versa.
-
SPLITFLAG
-
indicates that activities are allowed to be split into segments
during resource allocation. This option can be used instead of
specifying either the MAXNSEGMT= or the MINSEGMTDUR= variable;
PROC CPM assumes that the activity can be split into no more than
five segments.
-
STOPDATE=stdate
-
specifies the cutoff date for resource-constrained scheduling.
When such a date is specified, S_START and S_FINISH are set to
missing beyond the cutoff date. Options are available to set these
missing values to the original E_START and
E_FINISH times (FILLUNSCHED)
or to updated values based on the scheduled activities (UPDTUNSCHED).
-
T_FLOAT
-
requests that the Schedule data set include the T_FLOAT variable computed
using the unconstrained early and late start schedules. Note that if
resource allocation is not performed, this variable is always included in
the Schedule data set.
-
TOTUSAGE
- INTXRATE
- INTUSAGE
- RATEXINT
-
specifies that the Usage data set is to indicate the total usage
of the resource for the current time period. The current time
period is the time interval from the time specified
in the _TIME_
variable for the current observation to the time specified in the
_TIME_ variable for the next observation. The total usage is
computed taking into account the relevant activity and resource
calendars. Note that, by default, the observations in the Usage data
set specify the rate of usage for each resource at the beginning
of the current time period. The TOTUSAGE option specifies the
product of the rate and the time interval between two successive
observations. To get both the rate and the product, use the
APPEND option.
-
UNSCHEDMISS
-
sets the S_START and S_FINISH values to missing for activities that
are still unscheduled when resource constrained scheduling is stopped
either by the STOPDATE= option or due to resource infeasibilities.
This is the default and can be turned off
by specifying the FILLUNSCHED option.
-
UPDTUNSCHED
-
causes the procedure to use the S_START and S_FINISH times
of scheduled
activities to update the projected start and finish times
for the activities that
are still unscheduled when resource constrained scheduling is stopped
either by the STOPDATE= option or due to resource infeasibilities.
These updated dates are used as the
S_START and S_FINISH times.
-
WORK=variable
-
identifies a variable in the Activity data set that
specifies the total amount of work required by one unit
of a resource. This work is represented in units of
the INTERVAL parameter. The procedure uses the rate
specified for the resource variable to compute the
duration of the activity for that resource. Thus, if the value of the
WORK variable is 10, and the value of the
resource variable R1 is
2, then the activity requires 5 interval units for the
resource R1. For details, see the section "Resource-Driven Durations and Resource Calendars".