The Earned Value Management Macros

Performance Indices

Table 9.12 shows the formulas for Cost, Schedule, and To-Complete Performance Indices. WR is Work Remaining and is given by: {\rm wr = bac - ev}. the section "Cost Estimates" gives different expressions for the EAC (Estimate at Completion).

Table 9.12: Performance Index Formulas
Acronym Formula
CPI\frac{\rm ev}{\rm ac}
SPI\frac{\rm ev}{\rm pv}
{\rm tcpi_{\rm bac}}\frac{\rm wr}{\rm bac - ac}
{\rm tcpi_{\rm eac}}\frac{\rm wr}{\rm eac - ac}