| The Earned Value Management Macros | 
The ETC, or Estimate to Complete, and the EAC, or Estimate at Completion, are two metrics that are central to Earned Value Analysis. The ETC is a projection of the additional funds needed to finish the project. The EAC can be derived as follows (where AC represents the actual costs to date):

For the purposes of this document, each of these two cost estimates takes four forms, illustrated by the following table for ETC:
Table 9.13: ETC Formulas| Acronym | Description | Formula | 
| ETC  | Revised | EAC  - AC | 
| ETC  | Overrun to date | BAC - EV = WR | 
| ETC  | CPI |  | 
| ETC  | CPI times SPI |  | 
 
 The ETC is derived directly from the revised schedule, 
 revised costs, and actual costs to date.  This form does not make 
 allowances for past performance.  It is assumed that this 
 information has already been factored into the updated schedule 
 and costs. 
 
 
 Analogous to the ETC
 is derived directly from the revised schedule, 
 revised costs, and actual costs to date.  This form does not make 
 allowances for past performance.  It is assumed that this 
 information has already been factored into the updated schedule 
 and costs. 
 
 
 Analogous to the ETC , the ETC
, the ETC is taken to be the remaining planned value (Budget at Completion 
 less Earned Value), also known as Work Remaining (WR).  This 
 form can be thought of as having a performance factor of 1.
 
 is taken to be the remaining planned value (Budget at Completion 
 less Earned Value), also known as Work Remaining (WR).  This 
 form can be thought of as having a performance factor of 1.
 
 
 The ETC form is the 
 remaining planned value divided by the CPI. 
 In this way favorable cost performance 
 (CPI greater than 1) forces the estimate 
 downward.  The performance factor in this 
 case is the inverse of the CPI. 
 
 
 Similarly, 
 the ETC
 form is the 
 remaining planned value divided by the CPI. 
 In this way favorable cost performance 
 (CPI greater than 1) forces the estimate 
 downward.  The performance factor in this 
 case is the inverse of the CPI. 
 
 
 Similarly, 
 the ETC form employs 
 the inverse of the product of the CPI and SPI 
 as the performance factor.  In this case, 
 both cost and schedule performance affect 
 the estimate.  For example, if both CPI 
 and SPI are favorable (greater than 1), the 
 estimate is lower.
 form employs 
 the inverse of the product of the CPI and SPI 
 as the performance factor.  In this case, 
 both cost and schedule performance affect 
 the estimate.  For example, if both CPI 
 and SPI are favorable (greater than 1), the 
 estimate is lower.
 
Copyright © 2008 by SAS Institute Inc., Cary, NC, USA. All rights reserved.