The Earned Value Management Macros |
Table 9.11 shows the formulas for the Cost Variance, Schedule Variance, and Variance at Completion, along with the associated percentages.
Table 9.11: Variance FormulasAcronym | Formula |
CV | EV - AC |
CV% | ![]() |
SV | EV - PV |
SV% | ![]() |
VAC | BAC - EAC |
VAC% | ![]() |