Table 11.12 shows the formulas for Cost, Schedule, and To-Complete Performance Indices. WR is Work Remaining and is given by: . The section Cost Estimates gives different expressions for the EAC (Estimate at Completion).
Table 11.12: Performance Index Formulas
Acronym |
Formula |
CPI |
|
SPI |
|
|
|
|
|