This example shows how you can schedule the job over a nonstandard day and a nonstandard week. In the first part of the example, the calendar followed is a six-day week with an eight-and-a-half hour workday starting at 7 a.m. The project data are the same as were used in Example 4.8, but some of the durations have been changed to include some fractional values. Output 4.9.1 shows the project data set.
Output 4.9.1: Data Set WIDGET9: Scheduling on the Six-Day Week
Scheduling on the 6-Day Week |
Data Set WIDGET9 |
Obs | task | days | succ1 | succ2 | succ3 |
---|---|---|---|---|---|
1 | Approve Plan | 5.5 | Drawings | Study Market | Write Specs |
2 | Drawings | 10.0 | Prototype | ||
3 | Study Market | 5.0 | Mkt. Strat. | ||
4 | Write Specs | 4.5 | Prototype | ||
5 | Prototype | 15.0 | Materials | Facility | |
6 | Mkt. Strat. | 10.0 | Test Market | Marketing | |
7 | Materials | 10.0 | Init. Prod. | ||
8 | Facility | 10.0 | Init. Prod. | ||
9 | Init. Prod. | 10.0 | Test Market | Marketing | Evaluate |
10 | Evaluate | 10.0 | Changes | ||
11 | Test Market | 15.0 | Changes | ||
12 | Changes | 5.0 | Production | ||
13 | Production | 0.0 | |||
14 | Marketing | 0.0 |
The same Holiday data set is used. To indicate that work is to be done on all days of the week except Sunday, use INTERVAL=DTDAY
and define a Calendar data set with a single variable _SUN_, and a single observation identifying Sunday as a holiday. The
DATA step creating CALENDAR
and the invocation of PROC CPM is shown in the following code. Output 4.9.2 displays the resulting schedule.
/* Set up a 6-day work week, with Sundays off */ data calendar; _sun_='holiday'; run; title 'Scheduling on the 6-Day Week'; proc cpm data=widget9 holidata=holidays out=savec date='1dec03:07:00'dt interval=dtday daylength='08:30't calendar=calendar; activity task; succ succ1 succ2 succ3; duration days; holiday holiday / holifin=(holifin); run;
Output 4.9.2: Scheduling on the Six-Day Week
Scheduling on the 6-Day Week |
Project Schedule |
Obs | task | days | E_START | E_FINISH | L_START | L_FINISH | T_FLOAT | F_FLOAT |
---|---|---|---|---|---|---|---|---|
1 | Approve Plan | 5.5 | 01DEC03:07:00:00 | 06DEC03:11:14:59 | 01DEC03:07:00:00 | 06DEC03:11:14:59 | 0.0 | 0.0 |
2 | Drawings | 10.0 | 06DEC03:11:15:00 | 18DEC03:11:14:59 | 06DEC03:11:15:00 | 18DEC03:11:14:59 | 0.0 | 0.0 |
3 | Study Market | 5.0 | 06DEC03:11:15:00 | 12DEC03:11:14:59 | 15JAN04:11:15:00 | 21JAN04:11:14:59 | 30.0 | 0.0 |
4 | Write Specs | 4.5 | 06DEC03:11:15:00 | 11DEC03:15:29:59 | 13DEC03:07:00:00 | 18DEC03:11:14:59 | 5.5 | 5.5 |
5 | Prototype | 15.0 | 18DEC03:11:15:00 | 09JAN04:11:14:59 | 18DEC03:11:15:00 | 09JAN04:11:14:59 | 0.0 | 0.0 |
6 | Mkt. Strat. | 10.0 | 12DEC03:11:15:00 | 27DEC03:11:14:59 | 21JAN04:11:15:00 | 02FEB04:11:14:59 | 30.0 | 30.0 |
7 | Materials | 10.0 | 09JAN04:11:15:00 | 21JAN04:11:14:59 | 09JAN04:11:15:00 | 21JAN04:11:14:59 | 0.0 | 0.0 |
8 | Facility | 10.0 | 09JAN04:11:15:00 | 21JAN04:11:14:59 | 09JAN04:11:15:00 | 21JAN04:11:14:59 | 0.0 | 0.0 |
9 | Init. Prod. | 10.0 | 21JAN04:11:15:00 | 02FEB04:11:14:59 | 21JAN04:11:15:00 | 02FEB04:11:14:59 | 0.0 | 0.0 |
10 | Evaluate | 10.0 | 02FEB04:11:15:00 | 13FEB04:11:14:59 | 07FEB04:11:15:00 | 19FEB04:11:14:59 | 5.0 | 5.0 |
11 | Test Market | 15.0 | 02FEB04:11:15:00 | 19FEB04:11:14:59 | 02FEB04:11:15:00 | 19FEB04:11:14:59 | 0.0 | 0.0 |
12 | Changes | 5.0 | 19FEB04:11:15:00 | 25FEB04:11:14:59 | 19FEB04:11:15:00 | 25FEB04:11:14:59 | 0.0 | 0.0 |
13 | Production | 0.0 | 25FEB04:11:15:00 | 25FEB04:11:15:00 | 25FEB04:11:15:00 | 25FEB04:11:15:00 | 0.0 | 0.0 |
14 | Marketing | 0.0 | 02FEB04:11:15:00 | 02FEB04:11:15:00 | 25FEB04:11:15:00 | 25FEB04:11:15:00 | 20.0 | 20.0 |
Suppose now that you want to schedule work on a five-and-a-half day week (five full working days starting on Monday and half
a working day on Saturday). A full work day is from 8 a.m. to 4 p.m. Output 4.9.3 shows the data set WORKDAT
, which is used to define the work pattern for a full day (in the shift variable fullday
and a half-day (in the shift variable halfday
). Output 4.9.4 displays the Calendar data set, CALDAT
, which specifies the appropriate work pattern for each day of the week. The schedule produced by invoking the following program
is displayed in Output 4.9.5.
Output 4.9.3: Workday Data Set
Output 4.9.4: Calendar Data Set
proc cpm data=widget9 holidata=holidays out=savecw date='1dec03'd interval=day workday=workdat calendar=caldat; activity task; succ succ1 succ2 succ3; duration days; holiday holiday / holifin=(holifin); run;
Output 4.9.5: Scheduling on a Five-and-a-Half Day Week
Scheduling on a Five-and-a-Half-Day Week |
Project Schedule |
Obs | task | days | E_START | E_FINISH | L_START | L_FINISH | T_FLOAT | F_FLOAT |
---|---|---|---|---|---|---|---|---|
1 | Approve Plan | 5.5 | 01DEC03:08:00:00 | 06DEC03:11:59:59 | 01DEC03:08:00:00 | 06DEC03:11:59:59 | 0.0 | 0.0 |
2 | Drawings | 10.0 | 08DEC03:08:00:00 | 19DEC03:11:59:59 | 08DEC03:08:00:00 | 19DEC03:11:59:59 | 0.0 | 0.0 |
3 | Study Market | 5.0 | 08DEC03:08:00:00 | 12DEC03:15:59:59 | 20JAN04:08:00:00 | 26JAN04:11:59:59 | 30.0 | 0.0 |
4 | Write Specs | 4.5 | 08DEC03:08:00:00 | 12DEC03:11:59:59 | 15DEC03:08:00:00 | 19DEC03:11:59:59 | 5.5 | 5.5 |
5 | Prototype | 15.0 | 19DEC03:12:00:00 | 13JAN04:11:59:59 | 19DEC03:12:00:00 | 13JAN04:11:59:59 | 0.0 | 0.0 |
6 | Mkt. Strat. | 10.0 | 13DEC03:08:00:00 | 30DEC03:11:59:59 | 26JAN04:12:00:00 | 06FEB04:15:59:59 | 30.0 | 30.0 |
7 | Materials | 10.0 | 13JAN04:12:00:00 | 26JAN04:11:59:59 | 13JAN04:12:00:00 | 26JAN04:11:59:59 | 0.0 | 0.0 |
8 | Facility | 10.0 | 13JAN04:12:00:00 | 26JAN04:11:59:59 | 13JAN04:12:00:00 | 26JAN04:11:59:59 | 0.0 | 0.0 |
9 | Init. Prod. | 10.0 | 26JAN04:12:00:00 | 06FEB04:15:59:59 | 26JAN04:12:00:00 | 06FEB04:15:59:59 | 0.0 | 0.0 |
10 | Evaluate | 10.0 | 07FEB04:08:00:00 | 19FEB04:15:59:59 | 13FEB04:12:00:00 | 26FEB04:11:59:59 | 5.0 | 5.0 |
11 | Test Market | 15.0 | 07FEB04:08:00:00 | 26FEB04:11:59:59 | 07FEB04:08:00:00 | 26FEB04:11:59:59 | 0.0 | 0.0 |
12 | Changes | 5.0 | 26FEB04:12:00:00 | 03MAR04:15:59:59 | 26FEB04:12:00:00 | 03MAR04:15:59:59 | 0.0 | 0.0 |
13 | Production | 0.0 | 04MAR04:08:00:00 | 04MAR04:08:00:00 | 04MAR04:08:00:00 | 04MAR04:08:00:00 | 0.0 | 0.0 |
14 | Marketing | 0.0 | 07FEB04:08:00:00 | 07FEB04:08:00:00 | 04MAR04:08:00:00 | 04MAR04:08:00:00 | 20.0 | 20.0 |
Note that, in this case, it was not necessary to specify the DAYLENGTH=, DAYSTART=, or INTERVAL= option in the PROC CPM statement.
The default value of INTERVAL=DAY is assumed, and the CALDAT
and WORKDAT
data sets define the workday and work week completely. The length of a standard working day is also included in the Calendar
data set, completing all the necessary specifications.
To visualize the breaks in the work schedule created by these specifications, you can use the following simple data set with a dummy activity 'Schedule Breaks' to produce a Gantt chart, shown in Output 4.9.6. The period illustrated on the chart is from December 19, 2003 to December 27, 2003. The breaks are denoted by *.
/* To visualize the breaks, use following "dummy" data set to plot a schedule bar showing holidays and breaks */ data temp; e_start='19dec03:08:00'dt; e_finish='27dec03:23:59:59'dt; task='Schedule Breaks'; label task='Project Calendar'; format e_start e_finish datetime16.; run; title2 'Holidays and Breaks in the Project Calendar'; proc gantt data=temp lineprinter calendar=caldat holidata=holidays workday=workdat; chart / interval=dtday mininterval=dthour skip=0 holiday=(holiday) holifin=(holifin) markbreak nojobnum nolegend increment=8 holichar='*'; id task; run;
Output 4.9.6: Gantt Chart Showing Breaks and Holidays
Scheduling on a Five-and-a-Half-Day Week |
Holidays and Breaks in the Project Calendar |
DEC DEC DEC DEC DEC DEC Project 19 19 20 20 20 21 Calendar 08:00 16:00 00:00 08:00 16:00 00:00 -+-------+-------+-------+-------+-------+- Schedule Breaks |<-------****************----*************| -+-------+-------+-------+-------+-------+- |
Scheduling on a Five-and-a-Half-Day Week |
Holidays and Breaks in the Project Calendar |
DEC DEC DEC DEC DEC DEC DEC DEC 21 21 21 22 22 22 23 23 00:00 08:00 16:00 00:00 08:00 16:00 00:00 08:00 -+-------+-------+-------+-------+-------+-------+-------+- |********************************--------****************-| -+-------+-------+-------+-------+-------+-------+-------+- |
Scheduling on a Five-and-a-Half-Day Week |
Holidays and Breaks in the Project Calendar |
DEC DEC DEC DEC DEC DEC DEC DEC 23 23 24 24 24 25 25 25 08:00 16:00 00:00 08:00 16:00 00:00 08:00 16:00 -+-------+-------+-------+-------+-------+-------+-------+- |--------*************************************************| -+-------+-------+-------+-------+-------+-------+-------+- |
Scheduling on a Five-and-a-Half-Day Week |
Holidays and Breaks in the Project Calendar |
DEC DEC DEC DEC DEC DEC DEC DEC 25 26 26 26 27 27 27 28 16:00 00:00 08:00 16:00 00:00 08:00 16:00 00:00 -+-------+-------+-------+-------+-------+-------+-------+- |****************************************----*************| -+-------+-------+-------+-------+-------+-------+-------+- |