Table 4.1 outlines the options available for the CPM procedure, classified by function. An alphabetical list of options is provided in the Dictionary of Options.
Table 4.1: Functional Summary
| Description | Statement | Option | 
|---|---|---|
| Activity Splitting Specifications | ||
| Splits in-progress activities at TIMENOW | ||
| Specifies the maximum number of segments variable | ||
| Specifies the minimum segment duration variable | ||
| Enables splitting | ||
| Baseline or Target Schedule Specifications | ||
| Specifies the baseline finish date variable | ||
| Specifies the baseline start date variable | ||
| Specifies the schedule to compare with baseline | ||
| Specifies the schedule to use as baseline | ||
| Specifies the schedule to update baseline | ||
| Calendar Specifications | ||
| Specifies the calendar variable | ||
| Specifies the holiday variable | ||
| Specifies the holiday duration variable | ||
| Specifies the holiday finish variable | ||
| Data Set Specifications | ||
| Specifies the Calendar input data set | ||
| Specifies the Activity input data set | ||
| Specifies the Holiday input data set | ||
| Specifies the Schedule Output data set | ||
| Specifies the Resource Availability input data set | ||
| Specifies the Resource Schedule output data set | ||
| Specifies the Resource Usage output data set | ||
| Specifies the Workday input data set | ||
| Duration Control Specifications | ||
| Specifies the workday length | ||
| Specifies the workday start | ||
| Specifies the duration unit | ||
| Specifies the duration multiplier | ||
| Converts milestones into finish milestones | ||
| Specifies the duration variable | ||
| Specifies the finish variable | ||
| Overrides specified duration | ||
| Specifies the start variable | ||
| Specifies the work variable | ||
| Lag Specifications | ||
| Specifies the name of the lag duration calendar | ||
| Specifies the lag variables | ||
| Specifies the number of the lag duration calendar | ||
| Miscellaneous Options | ||
| Suppresses warning messages | ||
| Fixes L_FINISH for finish tasks to E_FINISH | ||
| Network Specifications | ||
| Specifies the AON format activity variable | ||
| Specifies the AOA format headnode variable | ||
| Specifies the project variable | ||
| Specifies the AON format successor variables | ||
| Specifies the AOA format tailnode variable | ||
| Multiproject Specifications | ||
| Specifies the project variable | ||
| Aggregates parent resources | ||
| Ignores parent resources | ||
| Computes separate critical paths | ||
| Uses specified project duration | ||
| Computes WBS Code | ||
| OUT= Data Set Options | ||
| Includes percent complete variable | ||
| Adds an observation for missing activities | ||
| Specifies single observation per activity | ||
| Copies relevant variables to Schedule data set | ||
| Specifies the variables to be copied to Schedule data set | ||
| Includes descending sort variables | ||
| Includes all sort order variables | ||
| Includes early start sort order variable | ||
| Includes late start sort order variable | ||
| Includes resource start order variable | ||
| Includes WBS Code | ||
| Includes information about resource delays | ||
| Includes early start schedule | ||
| Includes free float | ||
| Sets unscheduled S_START and S_FINISH | ||
| Includes late start schedule | ||
| Excludes early start schedule | ||
| Excludes free float | ||
| Excludes late start schedule | ||
| Excludes resource variables | ||
| Excludes total float | ||
| Includes resource variables | ||
| Includes total float | ||
| Sets unscheduled S_START and S_FINISH to missing | ||
| Updates unscheduled S_START, S_FINISH | ||
| Problem Size Options | ||
| Specifies the number of precedence constraints | ||
| Specifies the number of activities | ||
| Specifies the number of distinct node or activity names | ||
| Specifies the number of resource requirements | ||
| Disables use of the Utility data set | ||
| Progress Updating Options | ||
| Specifies the actual finish variable | ||
| Specifies the actual start variable | ||
| Assumes automatic completion | ||
| Enables actual time to fall in a non-work period | ||
| Does not assume automatic completion | ||
| Specifies the percentage complete variable | ||
| Specifies the remaining duration variable | ||
| Specifies that progress updating should override resource scheduling (Experimental) | ||
| Shows float for all activities | ||
| Specifies the current date | ||
| Resource Variable Specifications | ||
| Specifies the resource variables | ||
| Specifies the observation type variable | ||
| Specifies the resource availability date/time variable | ||
| Specifies the alternate resource variable | ||
| Specifies the work variable | ||
| Resource Allocation Control Options | ||
| Specifies the delay variable | ||
| Specifies the activity priority variable | ||
| Uses alternate resources before supplementary levels | ||
| Waits until L_START  | ||
| Specifies the delay | ||
| Schedules even if there are insufficient resources | ||
| Specifies independent allocation | ||
| Enables milestones to consume resources | ||
| Prevents milestones from consuming resources | ||
| Uses multiple alternates for a single resource | ||
| Specifies the resource calendar intersect | ||
| Specifies the scheduling priority rule | ||
| Specifies the secondary scheduling priority rule | ||
| Specifies the stop date for resource constrained scheduling | ||
| RESOURCEOUT= Data Set Options | ||
| Includes all types of resource usage | ||
| Appends observations for total usage | ||
| Specifies the name of the calendar for _TIME_ increment | ||
| Includes availability profile for each resource | ||
| Specifies the cumulative usage for consumable resources | ||
| Includes early start profile for each resource | ||
| Excludes unscheduled activities in profile | ||
| Includes unscheduled activities in profile | ||
| Records total usage of resource | ||
| Includes late start profile for each resource | ||
| Specifies the maximum value of _TIME_ | ||
| Specifies the maximum number of observations | ||
| Specifies the minimum value of _TIME_ | ||
| Specifies the numeric calendar for _TIME_ | ||
| Includes resource constrained profile | ||
| Specifies the unit of difference between consecutive _TIME_ values | ||
| Specifies the difference between consecutive _TIME_ values | ||
| Uses a continuous calendar for _TIME_ | ||
| RESOURCESCHED= Data Set Options | ||
| Adds activity or resource calendar | ||
| Includes WBS code | ||
| Includes order variables | ||
| Specifies the ID variables | ||
| Time Constraint Specifications | ||
| Specifies the alignment date variable | ||
| Specifies the alignment type variable | ||
| Specifies the project start date | ||
| Specifies the project finish date | ||
| Finishes before DATE= value | ||