

Table 4.1 outlines the options available for the CPM procedure, classified by function. An alphabetical list of options is provided in the Dictionary of Options.
Table 4.1: Functional Summary
|
Description |
Statement |
Option |
|---|---|---|
|
Activity Splitting Specifications |
||
|
Splits in-progress activities at TIMENOW |
||
|
Specifies the maximum number of segments variable |
||
|
Specifies the minimum segment duration variable |
||
|
Enables splitting |
||
|
Baseline or Target Schedule Specifications |
||
|
Specifies the baseline finish date variable |
||
|
Specifies the baseline start date variable |
||
|
Specifies the schedule to compare with baseline |
||
|
Specifies the schedule to use as baseline |
||
|
Specifies the schedule to update baseline |
||
|
Calendar Specifications |
||
|
Specifies the calendar variable |
||
|
Specifies the holiday variable |
||
|
Specifies the holiday duration variable |
||
|
Specifies the holiday finish variable |
||
|
Data Set Specifications |
||
|
Specifies the Calendar input data set |
||
|
Specifies the Activity input data set |
||
|
Specifies the Holiday input data set |
||
|
Specifies the Schedule Output data set |
||
|
Specifies the Resource Availability input data set |
||
|
Specifies the Resource Schedule output data set |
||
|
Specifies the Resource Usage output data set |
||
|
Specifies the Workday input data set |
||
|
Duration Control Specifications |
||
|
Specifies the workday length |
||
|
Specifies the workday start |
||
|
Specifies the duration unit |
||
|
Specifies the duration multiplier |
||
|
Converts milestones into finish milestones |
||
|
Specifies the duration variable |
||
|
Specifies the finish variable |
||
|
Overrides specified duration |
||
|
Specifies the start variable |
||
|
Specifies the work variable |
||
|
Lag Specifications |
||
|
Specifies the name of the lag duration calendar |
||
|
Specifies the lag variables |
||
|
Specifies the number of the lag duration calendar |
||
|
Miscellaneous Options |
||
|
Suppresses warning messages |
||
|
Fixes L_FINISH for finish tasks to E_FINISH |
||
|
Network Specifications |
||
|
Specifies the AON format activity variable |
||
|
Specifies the AOA format headnode variable |
||
|
Specifies the project variable |
||
|
Specifies the AON format successor variables |
||
|
Specifies the AOA format tailnode variable |
||
|
Multiproject Specifications |
||
|
Specifies the project variable |
||
|
Aggregates parent resources |
||
|
Ignores parent resources |
||
|
Computes separate critical paths |
||
|
Uses specified project duration |
||
|
Computes WBS Code |
||
|
OUT= Data Set Options |
||
|
Includes percent complete variable |
||
|
Adds an observation for missing activities |
||
|
Specifies single observation per activity |
||
|
Copies relevant variables to Schedule data set |
||
|
Specifies the variables to be copied to Schedule data set |
||
|
Includes descending sort variables |
||
|
Includes all sort order variables |
||
|
Includes early start sort order variable |
||
|
Includes late start sort order variable |
||
|
Includes resource start order variable |
||
|
Includes WBS Code |
||
|
Includes information about resource delays |
||
|
Includes early start schedule |
||
|
Includes free float |
||
|
Sets unscheduled S_START and S_FINISH |
||
|
Includes late start schedule |
||
|
Excludes early start schedule |
||
|
Excludes free float |
||
|
Excludes late start schedule |
||
|
Excludes resource variables |
||
|
Excludes total float |
||
|
Includes resource variables |
||
|
Includes total float |
||
|
Sets unscheduled S_START and S_FINISH to missing |
||
|
Updates unscheduled S_START, S_FINISH |
||
|
Problem Size Options |
||
|
Specifies the number of precedence constraints |
||
|
Specifies the number of activities |
||
|
Specifies the number of distinct node or activity names |
||
|
Specifies the number of resource requirements |
||
|
Disables use of the Utility data set |
||
|
Progress Updating Options |
||
|
Specifies the actual finish variable |
||
|
Specifies the actual start variable |
||
|
Assumes automatic completion |
||
|
Enables actual time to fall in a non-work period |
||
|
Does not assume automatic completion |
||
|
Specifies the percentage complete variable |
||
|
Specifies the remaining duration variable |
||
|
Specifies that progress updating should override resource scheduling (Experimental) |
||
|
Shows float for all activities |
||
|
Specifies the current date |
||
|
Resource Variable Specifications |
||
|
Specifies the resource variables |
||
|
Specifies the observation type variable |
||
|
Specifies the resource availability date/time variable |
||
|
Specifies the alternate resource variable |
||
|
Specifies the work variable |
||
|
Resource Allocation Control Options |
||
|
Specifies the delay variable |
||
|
Specifies the activity priority variable |
||
|
Uses alternate resources before supplementary levels |
||
|
Waits until L_START |
||
|
Specifies the delay |
||
|
Schedules even if there are insufficient resources |
||
|
Specifies independent allocation |
||
|
Enables milestones to consume resources |
||
|
Prevents milestones from consuming resources |
||
|
Uses multiple alternates for a single resource |
||
|
Specifies the resource calendar intersect |
||
|
Specifies the scheduling priority rule |
||
|
Specifies the secondary scheduling priority rule |
||
|
Specifies the stop date for resource constrained scheduling |
||
|
RESOURCEOUT= Data Set Options |
||
|
Includes all types of resource usage |
||
|
Appends observations for total usage |
||
|
Specifies the name of the calendar for _TIME_ increment |
||
|
Includes availability profile for each resource |
||
|
Specifies the cumulative usage for consumable resources |
||
|
Includes early start profile for each resource |
||
|
Excludes unscheduled activities in profile |
||
|
Includes unscheduled activities in profile |
||
|
Records total usage of resource |
||
|
Includes late start profile for each resource |
||
|
Specifies the maximum value of _TIME_ |
||
|
Specifies the maximum number of observations |
||
|
Specifies the minimum value of _TIME_ |
||
|
Specifies the numeric calendar for _TIME_ |
||
|
Includes resource constrained profile |
||
|
Specifies the unit of difference between consecutive _TIME_ values |
||
|
Specifies the difference between consecutive _TIME_ values |
||
|
Uses a continuous calendar for _TIME_ |
||
|
RESOURCESCHED= Data Set Options |
||
|
Adds activity or resource calendar |
||
|
Includes WBS code |
||
|
Includes order variables |
||
|
Specifies the ID variables |
||
|
Time Constraint Specifications |
||
|
Specifies the alignment date variable |
||
|
Specifies the alignment type variable |
||
|
Specifies the project start date |
||
|
Specifies the project finish date |
||
|
Finishes before DATE= value |
||