Progress/Baseline Information
This window is used to identify variables that contain activity progress information
and baseline schedules. For a description of standard import options, see the section "Standard Import Options".
The Actual Start variable should contain values that represent the actual
start date of the activity. This variable must be numeric.
The Actual Finish variable should contain values that represent the actual
finish date of the activity. This variable must be numeric.
The Percent Completed variable should contain values representing the
percentage of the activity that is completed. This variable must be numeric
and should contain values between 0 and 100.
The Remaining Duration variable should contain values that represent the
amount of time remaining for an activity that is in progress. This variable
must be numeric and should contain nonnegative values. The unit of duration
is assumed to be the same as that for the
Duration variable.
The Baseline Start variable should contain values that represent the baseline
start date of the activity. This variable must be numeric.
The Baseline Finish variable should contain values that represent the baseline
finish date of the activity. This variable must be numeric.