The PM Procedure |
Activities can be sorted by activity number, early start, late
start, and resource start by selecting Project->Sort from the
Project pull-down menu (see Figure 3.31). Once the activities are
sorted, the Schedule output data set contains the activities in the
new sorted order. See the section "Renumbering the Activities".