The GANTT Procedure

Example 6.13: Plotting the Resource-Constrained Schedule

This example illustrates plotting the resource-constrained schedules on a Gantt chart. The schedule used is the one produced in Example 2.19 using the CPM procedure. The output data set from PROC CPM is displayed in Output 6.13.1. Notice that the activities 'Drawings' and 'Mkt. Strat.' have been split to produce a shorter project duration than if they had not been split.

PROC GANTT is invoked with all default options and an ID statement. The early/late schedule is drawn on the first bar, and the resource-constrained schedule is drawn on the second bar of each activity. The observations corresponding to the split segments of each activity have been combined to produce the plot of the resource-constrained schedule for that activity. Thus, even though the Schedule data set input to PROC GANTT contains 18 observations, the Gantt chart shows each of the 14 activities only once.

  
    title 'Gantt Example 13'; 
    title2 'Resource Constrained Schedule'; 
  
    * plot the resource-constrained schedule using proc gantt; 
  
    proc gantt data=spltschd holidata=holdata; 
       chart / holiday=(hol) dur=days 
               height=1.5 pcompress; 
       id task; 
       run;
 

Output 6.13.1: Schedule Data Set SPLTSCHD
Gantt Example 13
Project Schedule: Splitting Allowed

Obs Task succ SEGMT_NO days prodman hrdware S_START S_FINISH E_START E_FINISH L_START L_FINISH
1 Approve Plan Drawings . 5 1 . 01DEC03 05DEC03 01DEC03 05DEC03 01DEC03 05DEC03
2 Drawings Prototype . 10 . 1 08DEC03 23DEC03 08DEC03 19DEC03 08DEC03 19DEC03
3 Drawings Prototype 1 2 . 1 08DEC03 09DEC03 08DEC03 19DEC03 08DEC03 19DEC03
4 Drawings Prototype 2 8 . 1 12DEC03 23DEC03 08DEC03 19DEC03 08DEC03 19DEC03
5 Anal. Market Mkt. Strat. . 5 . . 08DEC03 12DEC03 08DEC03 12DEC03 21JAN04 27JAN04
6 Write Specs Prototype . 5 . . 08DEC03 12DEC03 08DEC03 12DEC03 15DEC03 19DEC03
7 Prototype Materials . 15 1 . 24DEC03 15JAN04 22DEC03 13JAN04 22DEC03 13JAN04
8 Mkt. Strat. Test Market . 10 1 . 15DEC03 20JAN04 15DEC03 29DEC03 28JAN04 10FEB04
9 Mkt. Strat. Test Market 1 7 1 . 15DEC03 23DEC03 15DEC03 29DEC03 28JAN04 10FEB04
10 Mkt. Strat. Test Market 2 3 1 . 16JAN04 20JAN04 15DEC03 29DEC03 28JAN04 10FEB04
11 Materials Init. Prod. . 10 . . 16JAN04 29JAN04 14JAN04 27JAN04 14JAN04 27JAN04
12 Facility Init. Prod. . 10 . . 16JAN04 29JAN04 14JAN04 27JAN04 14JAN04 27JAN04
13 Init. Prod. Test Market . 10 1 . 30JAN04 12FEB04 28JAN04 10FEB04 28JAN04 10FEB04
14 Evaluate Changes . 10 1 . 13FEB04 26FEB04 11FEB04 24FEB04 18FEB04 02MAR04
15 Test Market Changes . 15 . . 13FEB04 04MAR04 11FEB04 02MAR04 11FEB04 02MAR04
16 Changes Production . 5 . . 05MAR04 11MAR04 03MAR04 09MAR04 03MAR04 09MAR04
17 Production   . 0 1 . 12MAR04 12MAR04 10MAR04 10MAR04 10MAR04 10MAR04
18 Marketing   . 0 . . 13FEB04 13FEB04 11FEB04 11FEB04 10MAR04 10MAR04



Output 6.13.2: Plotting the Resource-Constrained Schedule
ga13.gif (15275 bytes)


Previous Page | Next Page | Top of Page