Previous Page |
| |
Next Page |
Glossary of Earned Value Management Terms |
Glossary of Earned Value Management Terms
See
Actual Cost.
See
Actual Cost.
Total costs incurred that must relate to whatever cost
was budgeted within the
Planned Value and
Earned Value
(which can sometimes be direct labor hours
alone, direct costs alone, or all costs including indirect
costs) in accomplishing work during a given time period.
See
Actual Cost.
See
Budget at Completion.
See
Earned Value.
See
Planned Value.
The sum of the total budgets for a project.
See
Earned Value.
See
Planned Value.
See
Cost Performance Index.
See
Cost Variance.
See
Cost Variance Percentage.
The cost efficiency ratio of
Earned Value to
Actual Cost. CPI is often used to predict
the magnitude of a possible cost overrun using the following formula:
projected cost at completion.
.
The difference between the
Earned value of an activity and the
Actual Cost of that activity, i.e.,
.
Cost Variance relative to Earned Value:
.
See
Estimate at Completion.
See
Estimate to Complete.
See
Earned Value.
The physical work accomplished plus the authorized budget for this work.
The sum of the approved cost estimates (may include overhead allocation) for
activities (or portions of activities) completed during a given period (usually
project-to-date). Previously called the budgeted cost of work performed (BCWP)
for an activity or group of activities.
A method for integrating scope, schedule, and resources, and for measuring project
performance. It compares the value of work that was planned, the value of work that was actually
completed, and the amount of money that was actually spent, to determine if cost and schedule performance are
as planned.
The expected total cost of an activity, a group of activities, or the project when the defined
scope of work has been completed. Most techniques for producing the EAC include some adjustment
of the original cost estimate, based on actual project performance to date. This metric
is derived from the ETC as follows:
. See
Estimate to
Complete.
The expected additional cost needed to complete an activity, a group of activities,
or the project. Most techniques for producing the ETC factor in the project
performance to date. The revised ETC, or
, is the cumulative cost from
the status date to the project completion date, according to the revised
schedule and costs. The other three formulations used in this document are as follows:
See
Planned Value.
The percentage of total earned value that has been accumulated for a project:
.
The physical work scheduled, plus the authorized budget to accomplish
the scheduled work. Previously, this was called the budgeted cost of
work scheduled (BCWS).
See
Schedule Performance Index.
See
Schedule Variance.
See
Schedule Variance Percentage.
The schedule efficiency ratio of
Earned Value
accomplished against the
Planned Value.
The SPI describes what portion of the planned schedule was actually accomplished.
.
The difference between the
Earned value and the
Planned value of the project at any point in time, i.e.,
.
Schedule Variance relative to Planned Value:
.
See
To-Complete Performance Index.
The cost of remaining work divided by the remaining budget or estimated budget:
See
Variance at Completion.
See
Variance at Completion Percentage.
The difference between the original budget and the current estimate at completion:
.
The Variance at Completion relative to the Budget at Completion:
.
See
Work Breakdown Structure.
The project hierarchy.