| The Earned Value Management Macros |
Table 9.11 shows the formulas for the Cost Variance, Schedule Variance, and Variance at Completion, along with the associated percentages.
Table 9.11: Variance Formulas| Acronym | Formula |
| CV | EV - AC |
| CV% | |
| SV | EV - PV |
| SV% | |
| VAC | BAC - EAC |
| VAC% |