The Earned Value Management Macros |
%EVA_TASK_METRICS
This macro is used to produce earned value measures for each task; these measures
include Planned Value,
Earned Value, Actual Cost, Cost and Schedule Variance, and Cost and Schedule Performance Index.
- %EVA_TASK_METRICS ( parameters ) ;
Required Parameters
-
ACTIVITY=variable
- specifies the activity variable in the PLANSCHED= and REVISESCHED= data sets.
-
ACTUALCOST=SAS-data-set
-
-
REVISECOST=SAS-data-set
- identifies the updated costs data set.
-
BUDGETCOST=SAS-data-set
-
-
PLANCOST=SAS-data-set
- identifies the budgeted costs data set.
-
PLANSCHED=SAS-data-set
- identifies the input data set that contains the planned schedule.
-
REVISESCHED=SAS-data-set
- identifies the input data set that contains the updated schedule.
-
START=variable
- specifies the start date or datetime variable in the PLANSCHED= and REVISESCHED= data sets.
Optional Parameters
-
ACRONYMS=long
- specifies whether the long form of the earned value
acronyms is to be used - e.g., BCWP versus EV. The short form is used unless the macro variable
_ACRONYMS_ is set to "long" or ACRONYMS=long is specified. The parameter overrides
the macro variable setting;
i.e., specifying any non-null value other than "long" for the ACRONYMS= parameter produces short forms.
-
AGGREGATE=Y or otherwise
- specifies whether or not to roll up values along the project hierarchy;
a value of Y indicates that aggregation is to be carried out.
No rollup is performed for the default behavior. The WBSCODE=
parameter is required if AGGREGATE=Y is specified.
-
CALENDAR=SAS-data-set
- identifies the calendar data set. (See the CALENDAR= option in Chapter 2 of SAS/OR User's Guide: Project Management for more details.)
-
COST=variable
- specifies the cost variable in the BUDGETCOST= and ACTUALCOST= data sets. This is the
total of the start and finish costs associated with the given task. At least COST= or RATE=
must be specified. If a variable is specified for this
parameter, but the value for the variable is missing for a given observation, the
corresponding value from the BUDGETCOST= data set is used.
-
DURATION=variable
- specifies the task duration variable in the PLANSCHED= and REVISESCHED= data sets.
At least DURATION= or FINISH= must be specified.
If both
parameters are specified, the FINISH= variable value overrides
a nonzero DURATION= variable value; i.e., duration is only used to
indicate a milestone task.
-
FINISH=variable
- specifies the finish date or datetime variable in the PLANSCHED= and REVISESCHED= data sets
At least FINISH= or DURATION= must be specified.
If both
parameters are specified, the FINISH= variable value overrides
a nonzero DURATION= variable value; i.e., duration is only used to
indicate a milestone task.
-
HOLIDATA=SAS-data-set
- identifies the holiday data set. (See the HOLIDATA= option in Chapter 2 of SAS/OR User's Guide: Project Management for more details.)
-
HOLIDAY=statement
- specifies the HOLIDAY statement to use for PROC CPM. For example:
%eva_task_metrics(..., holiday=holiday start / holifin=finish, ...);
(See the HOLIDAY statement in Chapter 2 of SAS/OR User's Guide: Project Management for more details.)
-
INTERVAL=interval
- specifies the units to use for the DURATION= variable values. (See
the INTERVAL= option in Chapter 2 of SAS/OR User's Guide: Project Management for more details.)
-
PCTCOMP=variable
- specifies the percentage complete variable of the REVISESCHED= data set. Note that
for a given activity, the specified percentage complete can appear to be in conflict with the amount of
time spent, relative to the projected finish time for that activity. For example, even though 5 of 10
working days have elapsed, maybe only 30% of the activity has been completed. The input data
reflects an anticipated acceleration in progress over the next five days. Also, if there is
no value for the PCTCOMP= variable for a given activity, a computed value is substituted.
-
RATE=variable
- specifies the cost rate variable in the BUDGETCOST= and ACTUALCOST= data sets. This
is the rate at which cost is incurred over the DURATION= variable value for the given task.
At least RATE= or COST= must be specified. If a variable is specified for this
parameter, but the value for the variable is missing for a given observation, the
corresponding value from the BUDGETCOST= data set is used.
-
SPCT=variable
- specifies the start percentage variable in the BUDGETCOST= and ACTUALCOST= data sets.
This is the percentage of the COST= amount that is incurred at the beginning of the task. The
default is zero, in which case the entire COST= amount is incurred at the completion of the task.
The specified variable may also contain a comma-delimited list of weights to be used for
distributing the cost at equal working intervals over the duration of the activity.
If a variable is specified for this
parameter, but the value for the variable is missing for a given observation, the
corresponding value from the BUDGETCOST= data set is used.
-
TASKMETRICS=SAS-data-set
- identifies the output data set. The default data set name is TASKMETS.
-
TIMENOW=time
- specifies the date ('ddmmmyy'd) or datetime ('ddmmmyy:hh:mm:ss'dt)
of the updated schedule and costs. The default value is today's date unless
the macro variable _TIMENOW_ has been set, in which case the default
is the latter.
-
WBSCODE=variable
- specifies the variable containing the Work Breakdown Structure code in the PLANSCHED= or REVISESCHED= data set.
The default variable name is WBS_CODE.
-
WORKDAY=SAS-data-set
- identifies the workday input data set. (See the WORKDAY= option in Chapter 2 of SAS/OR User's Guide: Project Management for more details.)
Note that if a WORKDAY=, CALENDAR=, or HOLIDAY= data set is specified, the default variable name, _CAL_, is assumed for
calendar identification.
Figure 9.4 summarizes the parameters used
for managing input and output data sets in the %EVA_TASK_METRICS macro.
Table 9.4: %EVA_TASK_METRICS I/O Parameter Summary
Type
|
Data Set
|
Variables
|
INPUT | ACTUALCOST | COST, RATE, SPCT |
INPUT | BUDGETCOST | COST, RATE, SPCT |
INPUT | CALENDAR | |
INPUT | HOLIDATA | |
INPUT | PLANSCHED | ACTIVITY, DURATION, FINISH, START, WBSCODE |
INPUT | REVISESCHED | ACTIVITY, DURATION, FINISH, PCTCOMP, START, WBSCODE |
INPUT | WORKDAY | |
OUTPUT | TASKMETRICS | |
Copyright © 2008 by SAS Institute Inc., Cary, NC, USA. All rights reserved.