Problem Note 58844: Forecasts might not be available for products in regional promotions that were created from a copy
In SAS® Promotion Optimization, forecasts might not be available for products in regional promotions. This issue occurs when additional products are added to regional promotions and then the promotion is copied. When the additional products are added to the regional promotions, the scope is updated. However, when the promotion is copied, the scope of the master promotion overrides the updated scope in the regionals.
The workaround for this issue is to copy the promotion before adding extra products to regional promotions.
Click the Hot Fix tab in this note to access the hot fix for this issue.
Operating System and Release Information
SAS System | SAS Promotion Optimization | Linux for x64 | 5.2_M4 | 5.4 | 9.3 TS1M2 | 9.4 TS1M4 |
Microsoft® Windows® for x64 | 5.2_M4 | 5.4 | 9.3 TS1M2 | 9.4 TS1M4 |
*
For software releases that are not yet generally available, the Fixed
Release is the software release in which the problem is planned to be
fixed.
Type: | Problem Note |
Priority: | high |
Date Modified: | 2016-11-28 09:14:46 |
Date Created: | 2016-08-23 11:19:01 |