Problem Note 58273: SAS® Episode Analytics 3.1 - Expected cost not calculated when distribution model method is Tweedie and model type is two-part

DetailsHotfixAboutRate It

In SAS® Episode Analytics 3.1, when Tweedie is the selected distribution model method, the expected cost is not calculated for conditions that have 'two-part' selected as the model type.

The problem has been corrected and now the expected cost amounts, both TYPICAL and PAC, are calculated for the Tweedie distribution and two-part analysis model.



Operating System and Release Information

Product FamilyProductSystemProduct ReleaseSAS Release
ReportedFixed*ReportedFixed*
SAS SystemSAS Episode AnalyticsLinux for x642.2.23.1.19.4 TS1M3