Problem Note 58273: SASĀ® Episode Analytics 3.1 - Expected cost not calculated when distribution model method is Tweedie and model type is two-part
In SAS® Episode Analytics 3.1, when Tweedie is the selected distribution model method, the expected cost is not calculated for conditions that have 'two-part' selected as the model type.
The problem has been corrected and now the expected cost amounts, both TYPICAL and PAC, are calculated for the Tweedie distribution and two-part analysis model.
Operating System and Release Information
SAS System | SAS Episode Analytics | Linux for x64 | 2.2.2 | 3.1.1 | | 9.4 TS1M3 |
*
For software releases that are not yet generally available, the Fixed
Release is the software release in which the problem is planned to be
fixed.
SAS Note for defect S1236787 corrected in SEA Hot Fix 3.1.1 (Y93001)
Type: | Problem Note |
Priority: | high |
Date Modified: | 2016-05-31 11:10:26 |
Date Created: | 2016-05-24 21:55:14 |