SUPPORT / SAMPLES & SAS NOTES
 

Support

Problem Note 56377: Setting the relative period in a Performance Data-Entry portlet might show an incorrect date in non-English locales

DetailsHotfixAboutRate It

If you have a non-English locale in SAS® Strategy Management, an incorrect date might be displayed in the Performance Data-Entry portlet when you set the relative period.

This problem occurs after you perform the following steps:

  1. Click Edit Portlet in a Performance Data-Entry portlet to access the Edit Strategy Management Data Entry Portlet page.
  2. Click the Date tab, select the Relative period radio button, and enter a value in the field.
  3. Select a value from the Period type drop-down list and save your selections.

For example, the following screen shot shows a relative period setting in a user locale set to Italiano (Italia):

Relative period


Based on the setting of Periodo relative (Relative period) to -1 and Tipo di periodo (Period type) to Mese (Month) as shown above, the displayed date should be one month less than the current month. Instead, the actual displayed date is one year less than the current year.

Click the Hot Fix tab in this note to access the hot fix for this issue.



Operating System and Release Information

Product FamilyProductSystemProduct ReleaseSAS Release
ReportedFixed*ReportedFixed*
SAS SystemSAS Strategy ManagementMicrosoft® Windows® for x645.69.4 TS1M0
64-bit Enabled AIX5.69.4 TS1M0
64-bit Enabled Solaris5.69.4 TS1M0
Linux for x645.69.4 TS1M0
* For software releases that are not yet generally available, the Fixed Release is the software release in which the problem is planned to be fixed.