Problem Note 51757: Spend ($) values for actual periods are incorrect
When viewing the Plan Weekly Metrics table in the Plan Weekly Details view of SAS® Markdown Optimization, the Spend ($) value might be incorrect for the actualized periods. Typically, the spend value is understated because the software incorrectly calculates spend using end of period inventory instead of beginning of period inventory. The Spend ($) values in the frozen and future periods are correct.
There is no workaround for this issue.
Operating System and Release Information
SAS System | SAS High-Performance Markdown Optimization | Linux for x64 | 4.3_M2 | 5.2_M4 | 9.2 TS2M3 | 9.3 TS1M2 |
Microsoft® Windows® for x64 | 4.3_M2 | 5.2_M4 | 9.2 TS2M3 | 9.3 TS1M2 |
*
For software releases that are not yet generally available, the Fixed
Release is the software release in which the problem is planned to be
fixed.
Type: | Problem Note |
Priority: | high |
Date Modified: | 2014-03-05 09:20:15 |
Date Created: | 2013-12-05 10:38:47 |