Problem Note 35105: False alerts occur when a scenario is executed
The date calculation in scenario SAS10008 is incorrect. This might produce false alerts when the scenario is executed.
Select the Hot Fix tab in this note to access the hot fix for this issue.
The old date calculation was subtracting the current date from the number of calendar days within which an account had a transaction. The correct calculation should use the rundate instead of the current date.
Existing statement:
p10008_new_date = date() - &p10008_trans_days;
New statement:
p10008_new_date = rundate - &p10008_trans_days;
Operating System and Release Information
SAS System | SAS Money Laundering Detection | Microsoft Windows 2000 Advanced Server | 1.4 | 1.4 | 9.1 TS1M3 SP4 | 9.1 TS1M3 SP4 |
Microsoft Windows 2000 Datacenter Server | 1.4 | 1.4 | 9.1 TS1M3 SP4 | 9.1 TS1M3 SP4 |
Microsoft Windows 2000 Server | 1.4 | 1.4 | 9.1 TS1M3 SP4 | 9.1 TS1M3 SP4 |
Microsoft Windows 2000 Professional | 1.4 | 1.4 | 9.1 TS1M3 SP4 | 9.1 TS1M3 SP4 |
Microsoft Windows NT Workstation | 1.4 | 1.4 | 9.1 TS1M3 SP4 | 9.1 TS1M3 SP4 |
Microsoft Windows Server 2003 Datacenter Edition | 1.4 | 1.4 | 9.1 TS1M3 SP4 | 9.1 TS1M3 SP4 |
Microsoft Windows Server 2003 Enterprise Edition | 1.4 | 1.4 | 9.1 TS1M3 SP4 | 9.1 TS1M3 SP4 |
Microsoft Windows Server 2003 Standard Edition | 1.4 | 1.4 | 9.1 TS1M3 SP4 | 9.1 TS1M3 SP4 |
Microsoft Windows XP Professional | 1.4 | 1.4 | 9.1 TS1M3 SP4 | 9.1 TS1M3 SP4 |
Windows Vista | 1.4 | 1.4 | 9.1 TS1M3 SP4 | 9.1 TS1M3 SP4 |
*
For software releases that are not yet generally available, the Fixed
Release is the software release in which the problem is planned to be
fixed.
Scenario SAS10008 date calculation is incorrect. This may produce false alerts when the scenario is executed.
Type: | Problem Note |
Priority: | medium |
Date Modified: | 2009-03-25 15:13:02 |
Date Created: | 2009-03-11 16:43:34 |