Problem Note 10966: Scheduled tasks are not written to ISMTASKSCHED

DetailsAboutRate It
If multiple users all attempt to schedule multi-stage campaigns using
the SAS Campaign Management component such that two or more users
schedule their campaigns within a few seconds of one another, some tasks
may not be written to the ISMTASKSCHED table.  In some circumstances, if
the master task is not saved in ISMTASKSCHED, the whole communication
will fail to display in the Scheduled Tasks window.

To circumvent the problem, reschedule the tasks at a time when there
will be no conflict with other Campaign Management users.


A Technical Support hot fix for this issue is available at:
   http://ftp.sas.com/techsup/download/hotfix/cam75.html">http://ftp.sas.com/techsup/download/hotfix/cam75.html

After you apply the hotfix, you must ensure that the ISMTASKSCHED.TASKID
field is defined either with a Unique or Primary Key Constraint.


A Technical Support hot fix for this issue is available at:
http://ftp.sas.com/techsup/download/hotfix/cam75.html">http://ftp.sas.com/techsup/download/hotfix/cam75.html


Operating System and Release Information

Product FamilyProductSystemProduct ReleaseSAS Release
ReportedFixed*ReportedFixed*
SAS SystemSAS Campaign ManagementMicrosoft Windows NT Workstation7.57.5.2
Microsoft Windows XP Professional7.57.5.2
Microsoft Windows 2000 Professional7.57.5.2
Microsoft Windows 2000 Advanced Server7.57.5.2
Microsoft Windows 2000 Server7.57.5.2
Microsoft Windows 2000 Datacenter Server7.57.5.2
* For software releases that are not yet generally available, the Fixed Release is the software release in which the problem is planned to be fixed.