see timenow date .
see logical relationship .
the number of work periods (not including holidays or other nonworking periods) required to complete an activity or set of activities. All activity durations are specified with the same duration unit .
the unit of time that each activity in the project lasts. The following choices are available:
second
minute
hour
day
weekday
week
month
qtr
year