All the options that are available in the PROC CPM statement can also be specified in the PROC PM statement. See Chapter 4: The CPM Procedure, for details. However, there are a few additional options available with PROC PM, and some of the other PROC CPM options are
not needed as they are the default behavior in PROC PM. See Summary of Differences for more details about these differences.
Options Specific to PROC PM
The following options can be specified on the PROC PM statement.
-
NODISPLAY
-
invokes the procedure in a noninteractive mode. The schedule for the project is still computed and the requested output data
sets are created and saved. However, the PM window is not displayed. This option is useful for scheduling large projects that
do not need to be updated interactively. Note that invoking PROC PM with the NODISPLAY option is similar to invoking PROC
CPM; however, because the format of the Schedule output data set is different for the two procedures, you might see some differences
in the order and content of the observations. See Schedule Data Set for details.
-
PROJECT=
SAS-data-set
-
identifies a SAS data set that can be used to save and restore preferences that control the project view. For example, preferences
such as the font, column order, column widths, filters, and so forth, can be saved from one invocation to another. See PROJECT Data Set for more details about this data set and the preferences that can be saved in it.
-
PROJECTNAME=
’string’
PROJNAME=’string’
NAME=’string’
-
specifies a descriptive string identifying the name of the project. This string is used to label the PM window.
-
SUMMARYNAME=
’string’
SUMMARY=’string’
PROJECTSUMMARY=’string’
-
specifies a descriptive string identifying the summary task. By default, when there is more than one root parent activity
in a project, PROC PM creates a summary task named “Summary” (or “Project Summary” if the input format for the activity variable is 15 or greater). So, if there is already a child activity named “Summary” (or “Project Summary”) in the input data, the resulting schedule forms a cycle. The SUMMARYNAME= option enables you to override the default by
specifying a different name for the summary task, thereby avoiding the previously described problem.
Default Options for PROC PM Statement
The following options of PROC CPM are turned on by default in PROC PM.
-
ADDACT
ADDALLACT
EXPAND
-
indicates that an observation is to be added to the Schedule output data set (and the Resource Schedule output data set) for
each activity that appears as a value of the variables specified in the SUCCESSOR or PROJECT statements without appearing
as a value of the variable specified in the ACTIVITY statement. In other words, the Schedule output data set produced by PROC
PM contains one observation for every activity that appears as a value of the ACTIVITY, SUCCESSOR, or PROJECT variables (as
long as it has not been deleted in the current invocation of the procedure). It also contains an observation for every activity
that is added to the project using the graphical user interface.
-
XFERVARS
-
indicates that all relevant variables are to be copied from the Activity data set to the Schedule data set. The procedure
carries over to the output data set all the relevant variables from the input data set. Thus, the Schedule output data set
contains all the project information that is necessary to schedule it.
Default Options for ACTUAL Statement
-
AUTOUPDT
-
requests that the procedure assume automatic completion (or start) of activities that are predecessors to activities already
completed (or in progress).
-
ESTIMATEPCTC
ESTPCTC
ESTPCTCOMP
ESTPROG
-
indicates that a variable named PCT_COMP
is to be added to the Schedule output data set (and the Resource Schedule output data set) that contains the percent completion
time for each activity (for each resource used by each activity) in the project.
-
SHOWFLOAT
-
indicates that activities that are completed or in progress have nonzero float.
Default Options for PROJECT Statement
-
ADDWBS
WBSCODE
WBS
-
indicates that the PM procedure is to compute a WBS code for the activities in the project using the project hierarchy structure
specified. This code is computed for each activity and stored in the variable WBS_CODE
in the Schedule output data set.
-
DESCENDING
DESC
-
indicates that, in addition to the ascending sort variables (ES_ASC
, LS_ASC
, and SS_ASC
) that are requested by the ESORDER, LSORDER, and SSORDER options, the corresponding descending sort variables (ES_DESC
, LS_DESC
, and SS_DESC
, respectively) are also to be added to the Schedule output data set.
-
ESORDER
ESO
-
indicates that a variable named ES_ASC
is to be added to the Schedule output data set; this variable can be used to order the activities in such a way that the
activities within each subproject are in increasing order of the early start time. Note that this order is not necessarily
the same as the one that would be obtained by sorting all the activities in the Schedule data set by E_START
.
-
LSORDER
LSO
-
indicates that a variable named LS_ASC
is to be added to the Schedule output data set; this variable can be used to order the activities in such a way that the
activities within each subproject are in increasing order of the late start time.
-
ORDERALL
ALL
-
is equivalent to specifying the ESORDER and LSORDER options (and the SSORDER option when resource constrained scheduling is
performed).
-
SSORDER
SSO
-
indicates that a variable named SS_ASC
is to be added to the Schedule output data set; this variable can be used to order the activities in such a way that the
activities within each subproject are in increasing order of the resource-constrained start time.