Table 11.11 shows the formulas for the Cost Variance, Schedule Variance, and Variance at Completion, along with the associated percentages.
Acronym
Formula
CV
EV - AC
CV%
SV
EV - PV
SV%
VAC
BAC - EAC
VAC%