The Earned Value Management Macros |
Variances |
Table 11.11 shows the formulas for the Cost Variance, Schedule Variance, and Variance at Completion, along with the associated percentages.
Acronym |
Formula |
CV |
EV - AC |
CV% |
|
SV |
EV - PV |
SV% |
|
VAC |
BAC - EAC |
VAC% |
|