Previous Page | Next Page

The CPM Procedure

Example 4.24 Resource-Driven Durations and Resource Calendars

This example illustrates the effect of resource-driven durations and resource calendars on the schedule of a project involving multiple resources.

In projects that use manpower as a resource, the same activity may require different amounts of work from different people. Also, the work schedules and vacations may differ for each individual person. All of these factors may cause the schedules for the different resources used by the activity to differ from each other.

Consider a software project requiring two resources: a programmer and a tester. A network diagram displaying the activities and their precedence relationships is shown in Output 4.24.1.

Output 4.24.1 Software Project Network
Software Project Network

Some of the activities in this project have a fixed duration, requiring the same length of time from both resources; others require a different number of days from the programmer and the tester. Further, some activities require only a fraction of the resource; for example, 'Documentation' requires only 20 percent of the programmer’s time for a total of two man-days. The activities in the project, their durations (if fixed) in days, the total work required (if resource-driven) in days, the precedence constraints, and the resource requirements are displayed in Output 4.24.2. There are two observations for some of the activities ('Product Design' and 'Documentation') which require different amounts of work from each resource.

Output 4.24.2 Project Data
Software Development
Activity Data Set SOFTWARE

Activity act s1 s2 dur mandays Programmer Tester
Plans & Reqts 1 2 3 2 . 1.0 1.0
Product Design 2 4 5 . 3 1.0 .
Product Design 2 . . . 1 . 1.0
Test Plan 3 6 7 3 . . 1.0
Documentation 4 9 . . 2 0.2 .
Documentation 4 . . . 1 . 0.5
Code 5 8 . 10 . 0.8 .
Test Data 6 8 . 5 . . 0.5
Test Routines 7 8 . 5 . . 0.5
Test Product 8 9 . 6 . 0.5 1.0
Finish 9 . . 0 . . .

The following statements invoke PROC CPM with a WORK= specification on the RESOURCE statement, which identifies (in number of man-days, in this case) the amount of work required from each resource used by an activity. If the WORK variable has a missing value, the activity in that observation is assumed to have a fixed duration. The project is scheduled to start on April 12, 2004, and the activities are assumed to follow a five-day work week. Unlike fixed-duration scheduling, each resource used by an activity could have a different schedule; an activity is assumed to be finished only when all of its resources have finished working on it.

proc cpm data=software out=sftout ressched=rsftout
         date='12apr04'd interval=weekday resout=rout;
   act act;
   succ s1 s2;
   dur dur;
   res Programmer Tester / work=mandays
                        rschedid=Activity;
   id Activity;
run;

The individual resource schedules, as well as each activity’s combined schedule, are saved in a Resource Schedule data set, RSFTOUT, requested by the RESSCHED= option on the CPM statement. This output data set (displayed in Output 4.24.3) is very similar to the Schedule data set and contains the activity variable and all the relevant schedule variables (E_START, E_FINISH, L_START, and so forth).

Output 4.24.3 Resource Schedule Data Set
Software Development
Resource Schedule Data Set RSFTOUT

A
c
t
i
v
i
t
y
a
c
t
R
E
S
O
U
R
C
E
D
U
R
_
T
Y
P
E
d
u
r
m
a
n
d
a
y
s
R
_
R
A
T
E
E
_
S
T
A
R
T
E
_
F
I
N
I
S
H
L
_
S
T
A
R
T
L
_
F
I
N
I
S
H
Plans & Reqts 1     2 . . 12APR04 13APR04 12APR04 13APR04
Plans & Reqts 1 Programmer FIXED 2 . 1.0 12APR04 13APR04 12APR04 13APR04
Plans & Reqts 1 Tester FIXED 2 . 1.0 12APR04 13APR04 12APR04 13APR04
Product Design 2     3 . . 14APR04 16APR04 14APR04 16APR04
Product Design 2 Programmer RDRIVEN 3 3 1.0 14APR04 16APR04 14APR04 16APR04
Product Design 2 Tester RDRIVEN 1 1 1.0 14APR04 14APR04 16APR04 16APR04
Test Plan 3     3 . . 14APR04 16APR04 21APR04 23APR04
Test Plan 3 Tester FIXED 3 . 1.0 14APR04 16APR04 21APR04 23APR04
Documentation 4     10 . . 19APR04 30APR04 27APR04 10MAY04
Documentation 4 Programmer RDRIVEN 10 2 0.2 19APR04 30APR04 27APR04 10MAY04
Documentation 4 Tester RDRIVEN 2 1 0.5 19APR04 20APR04 07MAY04 10MAY04
Code 5     10 . . 19APR04 30APR04 19APR04 30APR04
Code 5 Programmer FIXED 10 . 0.8 19APR04 30APR04 19APR04 30APR04
Test Data 6     5 . . 19APR04 23APR04 26APR04 30APR04
Test Data 6 Tester FIXED 5 . 0.5 19APR04 23APR04 26APR04 30APR04
Test Routines 7     5 . . 19APR04 23APR04 26APR04 30APR04
Test Routines 7 Tester FIXED 5 . 0.5 19APR04 23APR04 26APR04 30APR04
Test Product 8     6 . . 03MAY04 10MAY04 03MAY04 10MAY04
Test Product 8 Programmer FIXED 6 . 0.5 03MAY04 10MAY04 03MAY04 10MAY04
Test Product 8 Tester FIXED 6 . 1.0 03MAY04 10MAY04 03MAY04 10MAY04
Finish 9     0 . . 11MAY04 11MAY04 11MAY04 11MAY04

For each activity in the project, the Resource Schedule data set contains the schedule for the entire activity as well as the schedule for each resource used by the activity. The variable RESOURCE identifies the name of the resource to which the observation refers and has missing values for observations that refer to the entire activity’s schedule. The value of the variable DUR_TYPE indicates whether the resource drives the activity’s duration ('RDRIVEN') or not ('FIXED').

The DURATION variable, dur, indicates the duration of the activity for the resource identified in that observation. For resources that are of the driving type, the WORK variable, mandays, shows the total amount of work (in units of the INTERVAL parameter) required by the resource for the activity in that observation. The variable R_RATE shows the rate of usage of the resource for the relevant activity. For driving resources, the variable dur is computed as (mandays / R_RATE). Thus, for the Activity, 'Documentation', the programmer requires 10 days to complete 2 man-days of work at a rate of 20 percent per day, while the tester works at a rate of 50 percent requiring 2 days to complete 1 man-day of work.



pattern1 c=green v=s;     /* duration of a non-critical activity   */
pattern2 c=green v=e;     /* slack time for a noncrit. activity    */
pattern3 c=red   v=s;     /* duration of a critical activity       */
pattern4 c=magenta v=e;   /* slack time for a supercrit. activity  */
pattern5 c=magenta v=s;   /* duration of a supercrit. activity     */
pattern6 c=cyan v=s;      /* actual duration of an activity        */
pattern7 c=black v=e;     /* break due to a holiday                */
pattern8 c=blue v=s;      /* resource schedule of activity         */
 pattern9 c=brown v=s;     /* baseline schedule of activity         */

title h=2 'Software Development';
title2 h=1.5 'Project Schedule';

A Gantt chart of the schedules for each resource is plotted in Output 4.24.4.

Output 4.24.4 Software Project Schedule
Software Project Schedule


The daily utilization of the resources is also saved in a data set, ROUT, displayed in Output 4.24.5. The resource usage data set indicates that you need more than one tester on some days with both the early schedule (on the 14th, 19th, and 20th of April) and the late schedule (on the 7th and 10th of May).

Output 4.24.5 Resource Usage Data
Software Development
Resource Usage Data Set ROUT

Obs _TIME_ EProgrammer LProgrammer ETester LTester
1 12APR04 1.0 1.0 1.0 1.0
2 13APR04 1.0 1.0 1.0 1.0
3 14APR04 1.0 1.0 2.0 0.0
4 15APR04 1.0 1.0 1.0 0.0
5 16APR04 1.0 1.0 1.0 1.0
6 19APR04 1.0 0.8 1.5 0.0
7 20APR04 1.0 0.8 1.5 0.0
8 21APR04 1.0 0.8 1.0 1.0
9 22APR04 1.0 0.8 1.0 1.0
10 23APR04 1.0 0.8 1.0 1.0
11 26APR04 1.0 0.8 0.0 1.0
12 27APR04 1.0 1.0 0.0 1.0
13 28APR04 1.0 1.0 0.0 1.0
14 29APR04 1.0 1.0 0.0 1.0
15 30APR04 1.0 1.0 0.0 1.0
16 03MAY04 0.5 0.7 1.0 1.0
17 04MAY04 0.5 0.7 1.0 1.0
18 05MAY04 0.5 0.7 1.0 1.0
19 06MAY04 0.5 0.7 1.0 1.0
20 07MAY04 0.5 0.7 1.0 1.5
21 10MAY04 0.5 0.7 1.0 1.5
22 11MAY04 0.0 0.0 0.0 0.0

Suppose now that you have only one tester and one programmer. You can determine a resource-constrained schedule using PROC CPM (as in the fixed duration case) by specifying a resource availability data set, RESIN (Output 4.24.6).

Output 4.24.6 Resource Availability Data
Software Development
Resource Availability Data Set

Obs per otype Programmer Tester
1 12APR04 reslevel 1 1


The following statements invoke PROC CPM, and the resulting Resource Schedule data set is displayed in Output 4.24.7. The ADDCAL option on the RESOURCE statement creates a variable in the Resource Schedule data set which identifies the activity or resource calendar. The project still finishes on May 11, but some of the activities ('Test Plan', 'Documentation', 'Test Data', and 'Test Routines') are delayed. The resource-constrained schedule is plotted on a Gantt chart in Output 4.24.8; both resources follow the same weekday calendar.

proc cpm data=software resin=resin
         out=sftout1 resout=rout1 
         rsched=rsftout1
         date='12apr04'd interval=weekday;
   act act;
   succ s1 s2;
   dur dur;
   res Programmer Tester / work=mandays addcal
                        obstype=otype
                        period=per
                        rschedid=Activity;
   id Activity;
run;

Output 4.24.7 Resource-Constrained Schedule: Common Calendar
Software Development
Resource Constrained Schedule: Common Resource Calendar

Activity act _CAL_ RESOURCE DUR_TYPE dur mandays R_RATE S_START S_FINISH E_START E_FINISH L_START L_FINISH
Plans & Reqts 1 0     2 . . 12APR04 13APR04 12APR04 13APR04 12APR04 13APR04
Plans & Reqts 1 0 Programmer FIXED 2 . 1.0 12APR04 13APR04 12APR04 13APR04 12APR04 13APR04
Plans & Reqts 1 0 Tester FIXED 2 . 1.0 12APR04 13APR04 12APR04 13APR04 12APR04 13APR04
Product Design 2 0     3 . . 14APR04 16APR04 14APR04 16APR04 14APR04 16APR04
Product Design 2 0 Programmer RDRIVEN 3 3 1.0 14APR04 16APR04 14APR04 16APR04 14APR04 16APR04
Product Design 2 0 Tester RDRIVEN 1 1 1.0 14APR04 14APR04 14APR04 14APR04 16APR04 16APR04
Test Plan 3 0     3 . . 15APR04 19APR04 14APR04 16APR04 21APR04 23APR04
Test Plan 3 0 Tester FIXED 3 . 1.0 15APR04 19APR04 14APR04 16APR04 21APR04 23APR04
Documentation 4 0     10 . . 27APR04 10MAY04 19APR04 30APR04 27APR04 10MAY04
Documentation 4 0 Programmer RDRIVEN 10 2 0.2 27APR04 10MAY04 19APR04 30APR04 27APR04 10MAY04
Documentation 4 0 Tester RDRIVEN 2 1 0.5 27APR04 28APR04 19APR04 20APR04 07MAY04 10MAY04
Code 5 0     10 . . 19APR04 30APR04 19APR04 30APR04 19APR04 30APR04
Code 5 0 Programmer FIXED 10 . 0.8 19APR04 30APR04 19APR04 30APR04 19APR04 30APR04
Test Data 6 0     5 . . 20APR04 26APR04 19APR04 23APR04 26APR04 30APR04
Test Data 6 0 Tester FIXED 5 . 0.5 20APR04 26APR04 19APR04 23APR04 26APR04 30APR04
Test Routines 7 0     5 . . 20APR04 26APR04 19APR04 23APR04 26APR04 30APR04
Test Routines 7 0 Tester FIXED 5 . 0.5 20APR04 26APR04 19APR04 23APR04 26APR04 30APR04
Test Product 8 0     6 . . 03MAY04 10MAY04 03MAY04 10MAY04 03MAY04 10MAY04
Test Product 8 0 Programmer FIXED 6 . 0.5 03MAY04 10MAY04 03MAY04 10MAY04 03MAY04 10MAY04
Test Product 8 0 Tester FIXED 6 . 1.0 03MAY04 10MAY04 03MAY04 10MAY04 03MAY04 10MAY04
Finish 9 0     0 . . 11MAY04 11MAY04 11MAY04 11MAY04 11MAY04 11MAY04

Output 4.24.8 Resource-Constrained Schedule
Resource-Constrained Schedule

Now suppose that the tester switches to part-time employment, working only four days a week. Thus, the two resources have different calendars. To determine the effect this change has on the project schedule, define a calendar data set identifying calendar '1' as having a holiday on Friday (see Output 4.24.9). In a new resource availability data set (also displayed in Output 4.24.9), associate calendar '1' with the resource Tester and calendar '0' with the resource Programmer. '0' refers to the default calendar, which is the weekday calendar for this project (since INTERVAL = WEEKDAY).

Output 4.24.9 Resource and Calendar Data
Software Development
Calendar Data Set CALENDAR

Obs _cal_ _fri_
1 1 holiday



Resource Data Set RESIN2

Obs per otype Programmer Tester
1 . calendar 0 1
2 12APR04 reslevel 1 1

Next, invoke PROC CPM, as shown in the following statements, with the Activity, Resource, and Calendar data sets to obtain the revised schedule, plotted in Output 4.24.10. The project is delayed by two days because of the TESTER’s shorter work week, which is illustrated by the longer holiday breaks in the TESTER’s schedule bars. The new resource constrained schedule is displayed in Output 4.24.11.

 proc cpm data=software resin=resin2
         caledata=calendar
         out=sftout2 rsched=rsftout2
         resout=rout2
         date='12apr04'd interval=weekday;
   act act;
   succ s1 s2;
   dur dur;
   res Programmer Tester / work=mandays addcal
                           obstype=otype
                           period=per
                           rschedid=Activity;
   id Activity;
 run;

Output 4.24.10 Resource-Constrained Schedule
Resource-Constrained Schedule

Output 4.24.11 Resource-Constrained Schedule: Multiple Calendars
Software Development
Resource Constrained Schedule: Multiple Resource Calendars

Activity act _CAL_ RESOURCE DUR_TYPE dur mandays R_RATE S_START S_FINISH E_START E_FINISH L_START L_FINISH
Plans & Reqts 1 0     2 . . 12APR04 13APR04 12APR04 13APR04 12APR04 13APR04
Plans & Reqts 1 0 Programmer FIXED 2 . 1.0 12APR04 13APR04 12APR04 13APR04 12APR04 13APR04
Plans & Reqts 1 1 Tester FIXED 2 . 1.0 12APR04 13APR04 12APR04 13APR04 12APR04 13APR04
Product Design 2 0     3 . . 14APR04 16APR04 14APR04 16APR04 14APR04 16APR04
Product Design 2 0 Programmer RDRIVEN 3 3 1.0 14APR04 16APR04 14APR04 16APR04 14APR04 16APR04
Product Design 2 1 Tester RDRIVEN 1 1 1.0 14APR04 14APR04 14APR04 14APR04 15APR04 15APR04
Test Plan 3 0     3 . . 15APR04 20APR04 14APR04 19APR04 19APR04 21APR04
Test Plan 3 1 Tester FIXED 3 . 1.0 15APR04 20APR04 14APR04 19APR04 19APR04 21APR04
Documentation 4 0     10 . . 29APR04 12MAY04 19APR04 30APR04 28APR04 11MAY04
Documentation 4 0 Programmer RDRIVEN 10 2 0.2 29APR04 12MAY04 19APR04 30APR04 28APR04 11MAY04
Documentation 4 1 Tester RDRIVEN 2 1 0.5 29APR04 03MAY04 19APR04 20APR04 10MAY04 11MAY04
Code 5 0     10 . . 19APR04 30APR04 19APR04 30APR04 19APR04 30APR04
Code 5 0 Programmer FIXED 10 . 0.8 19APR04 30APR04 19APR04 30APR04 19APR04 30APR04
Test Data 6 0     5 . . 21APR04 28APR04 20APR04 27APR04 22APR04 30APR04
Test Data 6 1 Tester FIXED 5 . 0.5 21APR04 28APR04 20APR04 27APR04 22APR04 29APR04
Test Routines 7 0     5 . . 21APR04 28APR04 20APR04 27APR04 22APR04 30APR04
Test Routines 7 1 Tester FIXED 5 . 0.5 21APR04 28APR04 20APR04 27APR04 22APR04 29APR04
Test Product 8 0     6 . . 04MAY04 12MAY04 03MAY04 11MAY04 03MAY04 11MAY04
Test Product 8 0 Programmer FIXED 6 . 0.5 04MAY04 11MAY04 03MAY04 10MAY04 04MAY04 11MAY04
Test Product 8 1 Tester FIXED 6 . 1.0 04MAY04 12MAY04 03MAY04 11MAY04 03MAY04 11MAY04
Finish 9 0     0 . . 13MAY04 13MAY04 12MAY04 12MAY04 12MAY04 12MAY04

Previous Page | Next Page | Top of Page