Resource Options  
 The 
Resource Cutoff Date field can be used to specify a cutoff date for resource leveling. 
 When this date is specified, the 
scheduled start and 
 
finish for activities that would 
 occur after the cutoff date are set to missing (empty).   This value 
 can be entered with either a DATEw. (that is, 01MAY2004) or a DATETIMEw. (that is, 
 01MAY2004:17:00:00) format.  Alternately, by clicking the 
Date: button, you can access 
 an 
Edit Date window to specify the desired value.
 
 The 
Default Maximum Activity Delay field can be used to specify the maximum amount of time 
 by which any activity in the project can be delayed due to lack of resources.  This 
 value acts as a default for all project activities, while individual values 
 can be specified for each separate activity.  The default value for this 
 option is +INFINITY.
 
 The maximum number of resource observations sets an upper limit on the number 
 of observations that the resource usage output data set can contain.  The default 
 value is 1000.  Use the horizontal slider to increase this limit.  The frequency 
 indicates the time interval at which observations are added to the data set.  Use 
 the 
Frequency box to select the desired time interval.
 
 When this check box is selected, the 
maximum activity delay 
 and each activity's 
delay values (if specified) are used 
 to control activity schedule slippage when performing resource leveling; otherwise, 
 the values are ignored and activity schedules are allowed to slip indefinitely.
 
 When this check box is selected, resource calendars (if specified) are 
 used to determine on/off work periods for resources; otherwise, all resource 
 calendars are ignored.
 
 When this check box is selected, activities are allowed to be split into 
 segments during resource allocation.  The 
maximum number of segments 
 and the 
minimum segment duration can be specified 
 for each activity to control the extent of the splitting.
 
 When this check box is selected, alternate resources (if specified) are used; 
 otherwise, they are ignored.
 
 This check box is used to activate resource-driven durations, provided that resources 
 have been defined as 
driving resources and work rates have been specified for 
 the activities.
 
 When this check box is selected, each resource can be scheduled separately for each 
 activity during resource allocation; otherwise, all resources (required by an 
 activity) must be available before work on the activity can be scheduled.  If 
 this check box is selected, each resource is scheduled independently of the others. 
 This may cause an activity's schedule to be extended if its resources cannot all 
 start at the same time.
 
 When this check box is selected, the scheduling algorithm continues to schedule 
 activities even when resources are insufficient.  By default, the algorithm 
 stops (with a partial schedule) when it cannot find sufficient resources for an 
 activity before the activity's latest possible start time (accounting for the 
 activity's 
delay value or the 
 
maximum activity delay and using supplementary or alternate 
 resources if necessary and if allowed).  This option is equivalent to specifying 
 infinite supplementary levels for all resources under consideration.
 
 When this check box is selected, an activity can be scheduled only during periods 
 that are common working times for all resource calendars (corresponding to the 
 resources used by that activity) and the activity's calendar.  Use this option 
 with caution; if an activity uses resources that have mutually disjoint calendars, 
 that activity can never be scheduled.
 
If this check box is cleared and resources have independent calendars, then 
 each resource is scheduled using its own calendar.  Thus, an activity can have 
 one resource working on a five-day calendar, while another resource is working 
 on a seven-day calendar.
 
 This check box indicates that the scheduling algorithm is to check for alternate 
 resources before using supplementary resources.  When this check box is cleared, the algorithm uses supplementary levels first (if available) and 
 alternate resources are used only if the supplementary levels are not sufficient.
 
 When this check box is selected, the scheduling algorithm waits until an 
 activity's 
late start plus 
 
delay before it is scheduled using a supplementary 
 level of resources.  Otherwise, even if an activity has a nonzero value 
 specified for delay, it can be scheduled using supplementary resources before 
 late start plus delay.