Previous Page | Next Page

The BOM Procedure

Example 3.2 Bill of Material with Lead Time Information

As in Example 3.1, this example also uses a single input data set with each observation containing product structure data and part master data. Unlike the SlBOM1 data set (shown in Output 3.1.1) in which each observation contains three product structure records, each observation in the input data set SlBOM2, as depicted in Output 3.2.1, contains only one product structure record. The observations in both input data sets also contain one part master record. However, in the previous example, the variable Parent contains the part number for the part master record, whereas in the current example, the part number for the part master record is contained in the variable Component. In addition, in this example, each part master record also contains requirement (contained in the Gros_Req variable) and quantity on hand (contained in the On_Hand variable) information.

Output 3.2.1 The Input Data Set (SlBOM2)
ABC Lamp Company
 
PROC BOM Input Data Set

Parent Component Desc Unit LeadTime QtyPer Gros_Req On_Hand
  LA01 Lamp LA Each 2 . 50 20
LA01 B100 Base assembly Each 1 1 . 50
LA01 S100 Black shade Each 2 1 . .
LA01 A100 Socket assembly Each 1 1 . .
B100 1100 Finished shaft Each 2 1 . .
B100 1200 6-Diameter steel plate Each 3 1 . .
B100 1300 Hub Each 2 1 . .
B100 1400 1/4-20 Screw Each 1 4 . .
A100 1500 Steel holder Each 2 1 . .
A100 1600 One-way socket Each 2 1 . .
A100 1700 Wiring assembly Each 1 1 . .
1100 2100 3/8 Steel tubing Inches 3 26 . .
1500 1400 1/4-20 Screw Each 1 2 . .
1700 2200 16-Gauge lamp cord Feet 2 12 . .
1700 2300 Standard plug terminal Each 1 1 . .

The following code produces the Indented BOM data set and the Summarized Parts data set. The Indented BOM data set, IndBOM2, is displayed in Output 3.2.2. The "PART=Component" specification in the STRUCTURE statement indicates that the Component variable contains the part number for the part master record in each observation. Since the LEADTIME= option is specified, a new variable, Tot_Lead, has been added to the Indented BOM data set. This variable denotes the total lead time accumulated from the root record (the top-most record) to the record identified by the value of the Part_ID variable.

  /* Create the indented BOM and the summarized parts list */
proc bom data=SlBOM2 out=IndBOM2 summaryout=SumBOM2;
   structure / part=Component
               leadtime=LeadTime 
               parent=Parent 
               component=Component
               quantity=QtyPer
               qtyonhand=On_hand 
               requirement=Gros_Req
               id=(Desc Unit);
run;

Output 3.2.2 Indented Bill of Material with Lead Time (IndBOM2)
ABC Lamp Company
 
Indented Bill of Material, Part LA01

_Level_ _Parent_ _Part_ Desc QtyPer Qty_Prod Unit LeadTime Tot_Lead _Prod_
0   LA01 Lamp LA . 1 Each 2 2 LA01
1 LA01 B100 Base assembly 1 1 Each 1 3 LA01
2 B100 1100 Finished shaft 1 1 Each 2 5 LA01
3 1100 2100 3/8 Steel tubing 26 26 Inches 3 8 LA01
2 B100 1200 6-Diameter steel plate 1 1 Each 3 6 LA01
2 B100 1300 Hub 1 1 Each 2 5 LA01
2 B100 1400 1/4-20 Screw 4 4 Each 1 4 LA01
1 LA01 S100 Black shade 1 1 Each 2 4 LA01
1 LA01 A100 Socket assembly 1 1 Each 1 3 LA01
2 A100 1500 Steel holder 1 1 Each 2 5 LA01
3 1500 1400 1/4-20 Screw 2 2 Each 1 6 LA01
2 A100 1600 One-way socket 1 1 Each 2 5 LA01
2 A100 1700 Wiring assembly 1 1 Each 1 4 LA01
3 1700 2200 16-Gauge lamp cord 12 12 Feet 2 6 LA01
3 1700 2300 Standard plug terminal 1 1 Each 1 5 LA01

Output 3.2.3 Summarized Parts List (SumBOM2)
ABC Lamp Company
 
Summarized Parts List, Period 2

_Part_ Low_Code Gros_Req On_Hand Net_Req LeadTime Desc Unit
1100 2 0 0 0 2 Finished shaft Each
1200 2 0 0 0 3 6-Diameter steel plate Each
1300 2 0 0 0 2 Hub Each
1400 3 60 0 60 1 1/4-20 Screw Each
1500 2 30 0 30 2 Steel holder Each
1600 2 30 0 30 2 One-way socket Each
1700 2 30 0 30 1 Wiring assembly Each
2100 3 0 0 0 3 3/8 Steel tubing Inches
2200 3 360 0 360 2 16-Gauge lamp cord Feet
2300 3 30 0 30 1 Standard plug terminal Each
A100 1 30 0 30 1 Socket assembly Each
B100 1 30 50 0 1 Base assembly Each
LA01 0 50 20 30 2 Lamp LA Each
S100 1 30 0 30 2 Black shade Each

The data set SumBOM2 displayed in Output 3.2.3 contains the sorted summarized parts list for the production plan, in which 50 units of 'Lamp LA' are planned (say, in period 2). Based on the input data, 'Lamp LA' has 20 units and 'Base assembly' has 50 units currently on hand. The gross requirements of 30 units for 'B100', 'S100', and 'A100' are from the net requirement of 'LA01' (computed as Gros_Req On_Hand). Since item 'B100' has 50 units on hand, which is more than its gross requirement, the net requirement of this item is 0. This implies that the gross requirements for '1100', '1200', and '1300' (components of the item 'B100') are all 0. However, the gross requirement for item '1400', which is also a component of 'B100', is not 0 but 60. This is due to the fact that item '1400' is also used in item '1500'.

The following code uses the Indented BOM data set produced in the previous invocation of PROC BOM to create a data set that can be used by the NETDRAW procedure.

     /* Prepare the data set for running NETDRAW */
   data IndBOM2a(drop=Part_ID);
      set IndBOM2;
      Paren_ID=Part_ID;
   run;

   data IndBOM2b;
      set IndBOM2(keep=Paren_ID Part_ID);
   run;

   data TreBOM2;
      set IndBOM2a IndBOM2b;
      LTnQP = put(LeadTime, f3.)||"  "||put(QtyPer, f3.);
   run;

PROC NETDRAW is invoked with the NODISPLAY option to create a data set (Layout2) that contains all the layout information for the tree structure. The OUT= option specifies the name of the layout data set:

  /* Specify graphics options */
title h=4pct j=c 'Multilevel Bill of Material with Lead-time Offsetting';
footnote h=3pct j=l 
         'Node shows Part Number, Lead-time, and Quantity Required';
pattern1 v=e c=blue;

  /* Get the layout information for the BOM tree */
proc netdraw data=TreBOM2( where=(Paren_ID NE .) ) 
             out=Layout2 nodisplay; 
   actnet / act=Paren_ID succ=Part_ID id=(_Part_ LTnQP Tot_Lead)
            ybetween=3 xbetween=15 tree 
            rectilinear nodefid nolabel;
run;

In the next invocation, PROC NETDRAW uses a modified layout of the nodes to produce a diagram where the nodes are aligned according to the total lead time. The resulting tree diagram is shown in Output 3.2.4. Refer to Chapter 7, The NETDRAW Procedure (SAS/OR 9.22 User's Guide: Project Management), for details about the NETDRAW procedure.

  /* Lead time offset the X coordinate of each node */
data TreBOM2a;
   set Layout2;
   if _seq_ = 0;
   drop _seq_;
   _x_ = Tot_Lead;
run;
  /* Display the BOM tree with lead-time offsetting */
proc netdraw data=TreBOM2a out=NetOUT;;
   actnet / id=(_Part_ LTnQP)
            ctext=black htext=3 carcs=black 
            align=Tot_Lead frame pcompress 
            xbetween=15 ybetween=3 
            arrowhead=0 rectilinear nodefid nolabel;
run;

Output 3.2.4 Bill of Material Diagram with Lead-time Offsetting
Bill of Material Diagram with Lead-time Offsetting

Previous Page | Next Page | Top of Page