Reasons why a network problem can be infeasible are similar to those previously mentioned but apply to a set of nodes rather than for an individual node.
Consider the network illustrated in Figure 5.10.
NODE_1----------------->NODE_2
/ capac=55 \
/ lo=50 \
/ \
/ \
/ \
NODE_3 NODE_4
supply=100 \ / demand=120
\ /
\ /
\ capac=62 /
\ lo=60 /
NODE_5----------------->NODE_6
Figure 5.10: An Infeasible Network
The demand of NODE_4 is 120. That can never be satisfied because the maximal flow through arcs (NODE_1, NODE_2) and (NODE_5, NODE_6) is 117. More specifically, the implicit supply of NODE_2 and NODE_6 is only 117, which is insufficient to satisfy the demand of other nodes (real or implicit) in the network.
Furthurmore, the lower flow bounds of arcs (NODE_1, NODE_2) and (NODE_5, NODE_6) are greater than the flow that can reach the tail nodes of these arcs, that, by coincidence, is the total supply of the network. The implicit demand of nodes NODE_1 and NODE_5 is 110, which is greater than the amount of flow that can reach these nodes.
|