| Product | Release |
|---|---|
| Base SAS | 9.2 |
| Previous Page | | | Next Page |
| The CALENDAR Procedure |
| Alias: | OUTSTA |
| Default: | If you do not use OUTSTART, then each calendar week begins with Sunday. |
| Featured in: | Multiple Schedule Calendars with Atypical Work Shifts (Separated Output) and Multiple Summary Calendars with Atypical Work Shifts (Separated Output) |
| OUTSTART day-of-week; |
| Required Arguments |
the name of the starting day of the week for each week in the calendar. For example,
outstart monday;
| Interaction with OUTDUR and OUTFIN |
By default, a calendar displays all seven days in a week. Use OUTDUR or OUTFIN, in conjunction with OUTSTART, to control how many days are displayed and which day starts the week.
| Previous Page | | | Next Page | | | Top of Page |