see schedule variance .
the schedule efficiency ratio of earned value
that was accomplished against the planned value
. The SPI describes what portion of the planned schedule was actually accomplished. .
the difference between the earned value
and the planned value
of the project at any point in time; that is, .
schedule variance relative to planned value: