Glossary of Project Management Terms


F

float

see total float .

forward pass

the calculation of the early start and early finish dates for the uncompleted portions of all network activities. See also backward pass .

free float (FF)

the amount of time an activity can be delayed without delaying the early start of any immediate successor activities. See also total float .