an activity that has low total float .
see network diagram .
the process of identifying early and late start and finish dates for the uncompleted portions of project activities. See also critical path method , program evaluation and review technique , and graphical evaluation and review technique .
a schematic display of the logical relationships of project activities. Always drawn from left to right to reflect project chronology. Often incorrectly referred to as a "PERT chart."
see logic .
any continuous series of connected activities that make up a project network diagram .
one of the defining points of a network; a junction point joined to some or all of the other dependency lines. Also, the graphic representation of an activity. See also arrow diagramming method and precedence diagramming method .
a dependency between two project activities that is not the standard finish-to-start relationship. See logical relationship for the four possible types of relationships.