The CPM Procedure |
Functional Summary |
The following tables outline the options available for the CPM procedure classified by function. An alphabetical list of options is provided in the Dictionary of Options.
Description |
Statement |
Option |
Split in-progress activities at TIMENOW |
||
Max. number of segments variable |
||
Min. segment duration variable |
||
Enable splitting |
Description |
Statement |
Option |
Baseline finish date variable |
||
Baseline start date variable |
||
Schedule to compare with baseline |
||
Schedule to use as baseline |
||
Schedule to update baseline |
Description |
Statement |
Option |
Calendar variable |
||
Holiday variable |
||
Holiday duration variable |
||
Holiday finish variable |
Description |
Statement |
Option |
Calendar input data set |
||
Activity input data set |
||
Holiday input data set |
||
Schedule output data set |
||
Resource availability input data set |
||
Resource schedule output data set |
||
Resource usage output data set |
||
Workday input data set |
Description |
Statement |
Option |
Workday length |
||
Workday start |
||
Duration unit |
||
Duration multiplier |
||
Treatment of milestone |
||
Duration variable |
||
Finish variable |
||
Override specified duration |
||
Start variable |
||
Work variable |
Description |
Statement |
Option |
Alphanumeric lag duration calendar |
||
Lag variables |
||
Numeric lag duration calendar |
Description |
Statement |
Option |
Suppress warning messages |
||
Fix L_FINISH for finish tasks to E_FINISH |
Description |
Statement |
Option |
AON format activity variable |
||
AOA format headnode variable |
||
Project variable |
||
AON format successor variables |
||
AOA format tailnode variable |
Description |
Statement |
Option |
Project variable |
||
Aggregate parent resources |
||
Ignore parent resources |
||
Compute separate critical paths |
||
Use specified project duration |
||
Compute WBS Code |
Description |
Statement |
Option |
Include percent complete variable |
||
Add an observation for missing activities |
||
Single observation per activity |
||
Copy relevant variables to Schedule data set |
||
variables to be copied to Schedule data set |
||
Include descending sort variables |
||
Include all sort order variables |
||
Include early start sort order variable |
||
Include late start sort order variable |
||
Include resource start order variable |
||
Include WBS Code |
||
Include information about resource delays |
||
Include early start schedule |
||
Include free float |
||
Set unscheduled S_START and S_FINISH |
||
Include late start schedule |
||
Exclude early start schedule |
||
Exclude free float |
||
Exclude late start schedule |
||
Exclude resource variables |
||
Exclude total float |
||
Include resource variables |
||
Include total float |
||
Set unscheduled S_START and S_FINISH to missing |
||
Update unscheduled S_START, S_FINISH |
Description |
Statement |
Option |
Number of precedence constraints |
||
Number of activities |
||
Number of distinct node or activity names |
||
Number of resource requirements |
||
Do not use utility data set |
Description |
Statement |
Option |
Actual finish variable |
||
Actual start variable |
||
Assume automatic completion |
||
Enable actual time to fall in a non-work period |
||
Do not assume automatic completion |
||
Percentage complete variable |
||
Remaining duration variable |
||
Show float for all activities |
||
Current date |
Description |
Statement |
Option |
Resource variables |
||
Observation type variable |
||
Resource availability date/time variable |
||
Alternate resource specification variable |
||
Work variable |
Description |
Statement |
Option |
---|---|---|
Delay variable |
||
Activity priority variable |
||
Use alternate resources before supplementary levels |
||
Wait until L_START DELAY |
||
Delay specification |
||
Schedule even if insufficient resources |
||
Independent allocation |
||
Milestones can consume resources |
||
Milestones can not consume resources |
||
Use multiple alternates for a single resource |
||
Resource calendar intersect |
||
Scheduling priority rule |
||
Secondary scheduling priority rule |
||
Stop date for resource constrained scheduling |
Description |
Statement |
Option |
Include all types of resource usage |
||
Append observations for total usage |
||
Alphanumeric calendar for _TIME_ |
||
Include availability profile for each resource |
||
Cumulative usage for consumable resources |
||
Include early start profile for each resource |
||
Exclude unscheduled activities in profile |
||
Include unscheduled activities in profile |
||
Save observations for total usage |
||
Include late start profile for each resource |
||
Maximum value of _TIME_ |
||
Maximum number of observations |
||
Minimum value of _TIME_ |
||
Numeric calendar for _TIME_ |
||
Include resource constrained profile |
||
Unit of difference between consecutive |
||
Difference between consecutive _TIME_ |
||
Use a continuous calendar for _TIME_ |
Description |
Statement |
Option |
Add activity or resource calendar |
||
Include WBS Code |
||
Include order variables |
||
Id variables |
Description |
Statement |
Option |
Alignment date variable |
||
Alignment type variable |
||
Project start date |
||
Project finish date |
||
Finish before DATE= value |
Copyright © SAS Institute, Inc. All Rights Reserved.