To run the migration wizard, navigate to the location
where you installed SAS Enterprise Guide. Then select
\4.3\MigrationWizard.exe
. Click
Enter to invoke the migration wizard. The first page of the migration
wizard opens. This page contains information about why you should
use this wizard and what you should do before you run the wizard.
Page 1 of the SAS Enterprise Guide Migration Wizard
On page 2 of the wizard,
verify the connection profile of the application server where your
information maps are located. You can click
Modify to change your connection profile.
On page 3 of the wizard,
select the files that you want to migrate. To do so, perform the
following steps:
-
To facilitate the selection
of files, from the drop-down list in the
Show field, select
SAS Enterprise Guide Projects (*.egp)
. This action causes only SAS Enterprise Guide projects to be displayed
in the
Available files column.
-
In the
Available
files column, navigate to the location of the SAS Enterprise
Guide projects that you want to migrate.
-
Check the boxes next
to the projects to be migrated.
-
Click the right arrow
to move the projects to the
Selected files column.
On page 4 of the wizard,
information is displayed that explains the next steps of the migration
process. Click
Next to run the process that
parses the files. The progress of the wizard is displayed as it locates
all the references to the projects that you selected.
Parsing Files Information Box
Click
Done when the progress indicator shows that this task is complete.
On page 5 of the wizard,
you must enter the new mapping information for the selected projects.
To do so, perform the following steps:
-
Use the
Show field to shorten the number of entries on this
page. From the drop-down list, select
Global references
only
. (This setting removes the information maps from
this page, which significantly simplifies the contents of this page.)
Selecting Only Global References
-
Expand the page to the
full width of your screen. This action enables you to have space to
see the complete path information for the current and new mappings.
-
If necessary, resize
the
Current Mapping column width so that
you can see the complete path. This path is the path that was used
in the SAS Enterprise Guide project when it was last saved. It identifies
the adapter and domain category for which the project was developed.
As shown in the following display, a typical path is quite long (for
example,
/Shared Data/SAS IT Resource Management/IT
Data Marts/VMwareForReporting2/VMware vCenter 1/Domain Categories/Guest
System/
).
Expanded Current Mapping Column
-
If you want to globally
change all references to the server, click the ellipsis button (
...) in the
New Mapping column.
The
Change Resource dialog box appears. Use
the
Browse button to display the list of
servers from which you can select the
Server name that you want to use in your paths. If you want to apply this change
to all the object references that contain this value, check the corresponding
box.
-
You must enter the mapping
information for your new IT data mart in the
New Mapping column for each of the project folders that are shown on this page.
To do so, perform the following steps:
-
Select the folder and
click the ellipsis button (
...) in the
New Mapping column. The
Change Resource dialog box appears.
-
Use the
Browse button to display the list of folders to which
the projects can be migrated. Expand the SAS Folders tree until you
locate the IT data mart from which you ran the
Adapter
Setup wizard for these projects.
Locating the IT Data Mart
-
Continue expanding the
folders within the IT data mart until you find the location of the
adapter and the domain category that corresponds to the path in the
Current Mapping field. In the
Select a Location dialog box, the
Selected location field
displays the complete path for the new location.
-
Make sure that the box
is checked that specifies to apply this change to all object references
that contain this value.
-
When you have entered
the new mapping information for all the SAS Enterprise Guide project
folders, click
Next.
-
On the
Begin
the migration process page, you can also enter the path
to your Migration Record File. You can also change the path to the
Log File, specify whether to create automatic backups of the original
files, and specify whether to verify the existence of all resources
that were changed.
Tip
For best results, specify
that the original files should be backed up automatically.
-
Click
Finish to perform the migration. The
Migrating files window displays the progress of your migration. When the migration
is complete, the status of the processing is displayed. If a processing
error occurred, you can view the log file. Otherwise, click
Done to exit from the migration wizard. The jobs that
contain the projects that were successfully migrated can be opened
in the IT data mart and run.